In the last two weeks:
- The Contractor completed installation of sheet piles at Shaw's Creek and excavation and removal of peat material underneath the existing roadway in the vicinity of the Creek.
- The Contractor commenced placement of new granular material for the road base
In the next two weeks:
- The Contractor will commence installation of ‘H’ piles for the new bridge abutments and continue earth works.