Queen Street East construction: Sep 18, 2018
From Serguei Kabanov, Project Manager
In the last two weeks, the Contractor:
+ Completed channel restoration and opened the Tributary to Shaw’s Creek and decommissioned temporary by-pass pipe
+ Completed the removal of sheet piles and backfilling of the new bridge abutment, West side
+ Commenced placement of sidewalks at the East Limit
+ Commenced excavation and forming foundation for the gateway monument
+ Continued installation of vegetated retaining walls
+ Continued placement of curbs for the new centre median islands
+ Continued road excavation and granular placement at the East Limit of the project
In the next two weeks, the Contractor will:
+ Continue installation of vegetated retaining walls
+ Continue road excavation and granular placement between the new culvert and bridge
+ Continue placement of curbs and sidewalks
+ Continue forming and pouring gateway monument
+ Commence and complete the delivery and installation of precast concrete girders for the new bridge
+ Commence forming, placing structural steel and pouring concrete for the new bridge, various components
+ Commence installation of decorative streetlight poles and underground wire at the East Limit of the project