Queen Street East construction: Sep 28, 2018
From Serguei Kabanov, Project Manager
In the last two weeks, the Contractor:
+ Completed forming, placing structural steel and pouring concrete for the new gateway monument footing
+ Completed installation of precast concrete girders for new bridge
+ Commenced placement of top soil at the East Limit
+ Commenced installation of decorative streetlight poles and underground wire at the East Limit of the project and mid-block
+ Continued installation of vegetated retaining walls
+ Continued placement of curbs and sidewalks
+ Continued road excavation and granular placement at the mid-block of the project
In the next two weeks, the Contractor will:
+ Continue installation of vegetated retaining walls
+ Continue placement of curbs and sidewalks
+ Continue forming and pouring gateway monument
+ Continue installation of decorative streetlight poles and underground wire mid-block
+Commence forming, placing structural steel and pouring concrete for the new bridge, various components
+ Commence road excavation and granular placement at the West Limit of the project