Alton Village Association
  • Home
  • Community Updates
  • Community Links
  • Alton Village Square
  • Community Gardens / Butterflyway
  • Discovery Guide
  • Events
  • Community Life / Visitor Information
  • History
    • Historical Perspective of Alton Village
  • About the A.V.A
  • Alton Neighbourhood Watch
  • Photo Gallery
  • Location
  • Contact Us

Update on Queen Street East from the Region of Peel

12/19/2018

0 Comments

 
Update on Phase 1 and 2
Alton Construction Dec 19, 2018
from Serguei Kabanov, Project Manager

THE ROAD IS NOW OPEN!! 
In the last two weeks, the Contractor:
+ Completed installation of the new Alton Grange sign
+ Completed installation of guide rail and chain link fence
+ Completed installation of luminaires, decorative pedestrian streetlight mast arms, banner arms and flower pot holders, throughout
+ Completed installation of signage
+ Completed temporary line painting/markings
+ Continued gateway monument construction; installed lettering

In the early 2019, the Contractor will:
+ Complete installation of bridge and culvert railings
+ Continue gateway monument construction, pending the weather (will not affect road operation)

In the Spring, 2019, the Contractor will come back to complete the following:
+ Complete gateway monument construction
+ Complete pattern colour concrete splash pad installation between the curb and the sidewalk, throughout (continuous pour to achieve uniform look)
+ Complete minor sidewalk installation
+ Complete colour staining of bridge and culvert parapet walls (continuous staining to achieve uniform look)
+ Install pier caps on bridge and culvert parapet walls
+ Complete outstanding driveway asphalt
+ Complete placement of top asphalt and permanent (durable) thermoplastic line markings
+ Complete final grading touch-ups, top soil, seeding and sod
+ Address final requests and deficiencies, if any

IMPORTANT INFORMATION FOR THE WINTER
PHASE 1:
+ Contractor will demobilize off site as of Wednesday, December 19, 2018. The Contractor provided emergency numbers and will be available to respond, if needed, over the winter months. Over the winter months, the roadway will be maintained by the Regional Operations Department.
+ Both site trailers will remain near the Pumping Station until the Spring. At that time, if our current Vendor is successful on winning Phase 2, both trailers will remain until December 2019. If not, they will be removed around May/June and a new Vendor will select a new location within Phase 2.
+ All newly constructed sidewalks will be kept closed until Spring 2019 due to: a small section of incomplete sidewalk around the bridge area, outstanding bridge and culvert railings and incomplete pattern colour concrete splash pads. Proper signage was placed. The Town of Caledon was notified. Sidewalks will not be plowed.
+ Newly constructed lay-by will be kept closed until Spring 2019 due to: incomplete permanent (durable) thermoplastic line markings for parking stalls and sidewalks being closed. Proper signage was placed. The Regional Operations Department was notified. Lay-by will not be plowed.
+ All newly installed ‘share the road’ signs (bicycle signage) will be bagged until Spring 2019 due to: incomplete permanent (durable) thermoplastic line markings.
+ Install and keep until March two Portable Variable Message Broads advising of the new speed limit and road conditions ahead

PHASE 2:
+ We are hoping to secure a Vendor for Phase 2 works by the end of February, 2019. The project will commence by the end of March
+ Enbridge Contractor will commence gas main relocations along Main Street South based on the following preliminary schedule:
+ Edmund Street to Station Street (east side of the road) – January to March
+ Queen Street to Edmund / Station Street to Beechgrove (east side of the road) – February to June
+ Most of the work will be done underground using directional drilling method. Sending and receiving shafts will be required at various locations. Some customers will be reconnected to the new main, once completed. Sub-station at N/W corner of McClellan Road will be relocated to S/W corner

0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    August 2023
    April 2023
    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.