+ Completed tendering processes and awarded Phase 2 works to Fermar Paving Limited http://www.fermarltd.com/
+ Staff are currently finalizing paperwork and executing the documents
+ The Contractor is anticipated to commence work mid to late March
*** Please note: Enbridge Gas Distribution retained NPL Canada https://nplcanada.ca/ to complete gas relocations in the Village. The contractor will be mobilizing the site this week, February 28/19, weather permitting. Work will commence in phases:
Phase 1:
+ Station Street to Edmund Street
Phase 2:
+ Main/Queen Intersection to Edmund Street
+ Station Street to McClellan Road
Work will include:
+ Relocation of gas mains and services along Main Street South, between Queen Street East and Beechgrove Sideroad
+ Relocation of gas substation from N/W to S/W corner of McClellan Road