Update from the Region of Peel on Alton Village Streetscaping from Serguei Kabanov, Project Manager

5/27/2020

0 Comments

 
PHASE 2:
The roadway remains open with temporary lane closures:
• Main Street South, North of Beechgrove (around the Southern island) – East side of the roadway remains temporary closed – signals in place; and,
• Main Street South, between Station and South of King (at cemetery slope) – West side of the roadway remains temporary closed – signals in place;
​
In the last two weeks, the Contractor:
o Completed placement of top soil and terraseeding on Main Street, from Beechgrove to North, East side
o Completed placement of armour stone at median island, North of Beechgrove
o Completed installation of sprinklers at both gateway islands on Main Street, North of Beechgrove
o Completed installation of the flood light at gateway monument
o Completed installation of three centre median islands on Main Street, South of McClellan
o Completed installation of permeable pavers at parkette area at Main/Queen Intersection
o Completed installation of Canada Post pad on King Street, West of Main
o Completed clock turn-on
o Continued driveways reconstruction
o Continued installation of streetlight back shields on Main Street and McClellan
o Continued stone work at the retaining wall adjacent to the cemetery
o Commenced installation of pattern colour concrete splash pads on Main Street, from Main/Queen Intersection to South
o Commenced installation of decorative bollards at the parkette, cemetery retaining wall and McClellan Intersection
o Commenced boulevard grading, throughout
​
In the next two weeks, the Contractor will:
o Complete installation of decorative bollards at the parkette, cemetery retaining wall and McClellan Intersection
o Complete installation of pattern colour concrete splash pads on Main Street, from Main/Queen Intersection to South
o Continue driveways reconstruction
o Commence installation of decorative fencing at the retaining wall adjacent to the cemetery
o Commence installation of street furniture, throughout
o Commence placement of top soil and shrubs/trees
o Commence installation of armour stone retaining walls, throughout
0 Comments

Update Alton Village Streetscaping from Serguei Kabanov Project Manager

5/13/2020

0 Comments

 

PHASE 2:
The roadway remains open with temporary lane closures:
Main Street South, North of Beechgrove (around the Southern island) – East side of the roadway remains temporary closed – signals in place; and, Main Street South, between South of Alton Greenhouses and McClellan Road – East side of the roadway remains temporary closed – signals in place. Main Street South, between Station and South of King (at cemetery slope) – West side of the roadway remains temporary closed – signals in place; 

In the last two weeks, the Contractor:
​​
+ Completed installation of rest area/Canada Post pad on Main Street, South of McClellan
+ Completed grading, forming and pouring concrete sidewalk along the West side of Main Street, South of McClellan
+ Completed grading, forming and pouring concrete sidewalk along the North side of McClellan, between Main and Agnes
+ Completed grading, forming and pouring concrete sidewalk along the retaining wall adjacent to the cemetery
+ Completed masonry work at Gateway monument, on Main Street
+ Completed installation of permeable pavers at on-street lay-bys along the West side of Main Street, South of McClellan
+ Completed pouring curbs for flower beds along the East side of Main Street, from Station to Main/Queen Intersection, including parkette area
+ Completed adjustments and repairs to curbs and sidewalks
+ Completed backfilling the retaining wall adjacent to the cemetery
+ Completed straightening streetlight poles on Main Street and McClellan
+ Continued driveways reconstruction
+ Commenced stone work at the retaining wall adjacent to the cemetery
+ Commenced placement of top soil and terraseeding on Main Street, from Beechgrove to North, West side
+ Commenced installation of three centre median islands on Main Street, South of McClellan


In the next two weeks, the Contractor will:
+ Complete installation of decorative fencing at the retaining wall adjacent to the cemetery
+ Complete installation of Canada Post pad on King Street, West of Main
+ Complete placement of armour stone at median island, North of Beechgrove
+ Complete installation of sprinklers at both gateway islands on Main Street, North of Beechgrove
+ Complete installation of three centre median islands on Main Street, South of McClellan
+ Continue stone work at the retaining wall adjacent to the cemetery
+ Continue placement of top soil and terraseeding on Main Street, from Beechgrove to North, East side
+ Commence installation of pattern colour concrete splash pads on Main Street, from Main/Queen Intersection to South
+ Commence and complete installation of permeable pavers at parkette area at Main/Queen Intersection
+ Commence and complete installation of streetlight back shields on Main Street and McClellan

 
​

0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.