Update on Queen Street East from the Region of Peel

9/28/2018

0 Comments

 
Update on the Phase 1 
Queen Street East construction: Sep 28, 2018
From Serguei Kabanov, Project Manager

In the last two weeks, the Contractor:
+ Completed forming, placing structural steel and pouring concrete for the new gateway monument footing
+ Completed installation of precast concrete girders for new bridge
+ Commenced placement of top soil at the East Limit
+ Commenced installation of decorative streetlight poles and underground wire at the East Limit of the project and mid-block
+ Continued installation of vegetated retaining walls 
+ Continued placement of curbs and sidewalks
+ Continued road excavation and granular placement at the mid-block of the project

In the next two weeks, the Contractor will:
+ Continue installation of vegetated retaining walls
+ Continue placement of curbs and sidewalks
+ Continue forming and pouring gateway monument
+ Continue installation of decorative streetlight poles and underground wire mid-block
+Commence forming, placing structural steel and pouring concrete for the new bridge, various components
+ Commence road excavation and granular placement at the West Limit of the project
0 Comments

Update on Queen Street East from the Region of Peel

9/18/2018

0 Comments

 
Update on the Phase 1 
Queen Street East construction: Sep 18, 2018
From Serguei Kabanov, Project Manager

In the last two weeks, the Contractor:
+ Completed channel restoration and opened the Tributary to Shaw’s Creek and decommissioned temporary by-pass pipe
+ Completed the removal of sheet piles and backfilling of the new bridge abutment, West side
+ Commenced placement of sidewalks at the East Limit
+ Commenced excavation and forming foundation for the gateway monument
+ Continued installation of vegetated retaining walls
+ Continued placement of curbs for the new centre median islands
+ Continued road excavation and granular placement at the East Limit of the project
 
In the next two weeks, the Contractor will:
+ Continue installation of vegetated retaining walls
+ Continue road excavation and granular placement between the new culvert and bridge
+ Continue placement of curbs and sidewalks
+ Continue forming and pouring gateway monument
+ Commence and complete the delivery and installation of precast concrete girders for the new bridge
+ Commence forming, placing structural steel and pouring concrete for the new bridge, various components
+ Commence installation of decorative streetlight poles and underground wire at the East Limit of the project
0 Comments

Bridge and Road Rehabilitation on Highpoint Side Road

9/18/2018

0 Comments

 
Highpoint Side Road will be closed between Porterfield Road and Willoughby Road for local 
railway maintenance. Local access will be maintained however, due to the nature of the project, Highpoint Side Road will be closed to through traffic.
Anticipated construction dates:
Monday, September 24, 2018 (anticipated road closure date)
Sunday, September 30, 2018 (anticipated completion date)
 
There will be no through traffic on Highpoint Side road during the road closure.
All questions regarding this project can be directed to Service Caledon at:
905 584 2272 x.7750

Picture
0 Comments

Public Notice from the Region of Peel Public Works

9/11/2018

0 Comments

 
SCHEDULED WATER SUPPLY INTERRUPTION
 
Dear Customer:
 
The Region of Peel Public Works department regularly maintains and repairs the water system to make sure you have a reliable supply of quality drinking water. Sometimes we must turn off your water supply while we do the work. In the next few days, we will be working in your area and will have to turn off your water for a few hours.
 
Your water will be turned off on Monday, September 17, 2018 from approximately 12:00 p.m. to 4:00 p.m. However, if the weather is bad or if a problem arises, we will reschedule the work and will let you know the new date and time.
 
When we turn the water back on, air in the pipes may make the water cloudy and your plumbing may vibrate or make noise. If this happens, you can remove the air by briefly turning on your taps from the lowest to the highest faucet in the building (that is, starting in the basement/first floor and finishing on the top floor). Flush the toilets as well.
 
You should only have to run the water for 10 to 30 seconds, but keep running it until the water is clear, and any vibration or noise has stopped.
 
If your water meter starts to leak, call Water Meter Installations Dispatch at:
(905) 791-7800 Ext. 3226 (8:30 a.m. to 4:30 p.m. - Monday to Friday)
(905) 791-7800 Ext. 4409 (After hours or Statutory Holidays)
 

 
Date and Time: Monday, September 17, 2018 from 12:00 p.m. to 4:00 p.m.
 
Location: 2938 Charleston Sideroad, Caledon
 
Addresses Affected:  #’s 2940, 2939 and 2943 Charleston Sideroad
                                    #2 McFaul Street
                                    #155 Troiless Street
                                    #28 Elizabeth Street  

  
Shaun Hussain
Foreman, Construction Inspection
Engineering Technical Services
Operations Support
Public Works Department
0 Comments

Update on Queen Street East from the Region of Peel

9/4/2018

0 Comments

 
Update on the Phase 1 
Queen Street East construction: Sep 4, 2018
From Serguei Kabanov, Project Manager
In the last two weeks, the Contractor:

  • Completed forming, placement of reinforcing steel and pouring concrete for the new bridge abutment, West side
  • Completed forming, placement of reinforcing steel and pouring concrete for pre-cast arch culvert wing walls, South side
  • Commenced installation of vegetated retaining walls near pre-cast arch culvert
  • Continued backfilling pre-cast arch culvert
In the next two weeks, the Contractor will:

  • Continue installation of vegetated retaining walls and backfilling pre-cast arch culvert
  • Continue placement of curbs and sidewalks
  • Complete channel restoration and open the Tributary and decommission temporary by-pass pipe
  • Complete the removal of sheet piles and backfilling of the new bridge abutment, West side
  • Commence forming ballast walls at the new bridge abutments, East and West sides
Serguei will continue to provide updates with major milestones and highlights of the project
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.