Alton Village Association
  • Home
  • Community Updates
  • Community Links
  • Alton Village Square
  • Community Gardens / Butterflyway
  • Events
  • Community Life / Visitor Information
  • History
    • Historical Perspective of Alton Village
  • About the A.V.A
  • Alton Neighbourhood Watch
  • Photo Gallery
  • Location
  • Contact Us
  • Non-clickable Page

All Candidates Community Meeting for Ward 1

7/30/2018

0 Comments

 
Picture
0 Comments

Update on Queen Street East from the Region of Peel

7/24/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel
​

I would like to provide you with a quick update on the Phase 1 – Queen Street East construction:
In the last two weeks, the Contractor:
o Completed installation of ‘H’ piles for the new bridge abutments, East side
o Completed pouring concrete for pre-cast arch culvert footing, West side
o Commenced excavation, forming, placement of reinforcing steel and pouring concrete for pre-cast arch culvert footing, East side
o Completed existing bridge removal
o Completed installation of pre-cast arch culvert and commenced backfilling
o Commenced excavation, forming, placement of reinforcing steel new bridge footing, East side
o Commenced pouring new concrete curbs on the East side of the Creek
o Commenced Tributary to Shaw’s Creek restoration
​

In the next two weeks, the Contractor will:
o Continue backfilling pre-cast arch culvert
o Continue Tributary to Shaw’s Creek restoration
o Complete the removal of existing bridge footings, both sides
o Complete pouring concrete for the new bridge abutment, East side
o Commence excavation for the new bridge abutment, West side
o Commence installation of ‘H’ piles for the new bridge abutments, West side
o Commence underground electrical works
0 Comments

Update on Queen Street East from the Region of Peel

7/23/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel

This afternoon, the Contractor successfully installed pre-cast arch culvert over the Tributary to Shaw’s creek.

​
Picture
0 Comments

Update on Queen Street East from the Region of Peel

7/20/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel

This morning, the Contractor successfully removed existing bridge over Shaw’s creek.
0 Comments

Update on Queen Street East from the Region of Peel

7/10/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel
 
In the last two weeks, the Contractor:
+ Completed installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
+ Completed pouring concrete for pre-cast arch culvert footing, West side
+ Completed the removal of existing concrete box culvert for Tributary to the Shaw’s Creek
+ Completed storm sewer installation on the West side of the Creek
+ Commenced excavation, forming, placement of reinforcing steel for pre-cast arch culvert footing, East side
+ Commenced pouring new concrete curbs on the East side of the Creek
+ Continued building proposed roadway on the East side of the Creek by placing limestone materials
In the next two weeks, the Contractor will:
+ Continue pouring new concrete curbs on the East side of the Creek
+ Complete Tributary to the Shaw’s Creek restoration
+ Complete pouring concrete for pre-cast arch culvert footing, East side
+ Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek
+ Commence and complete Tributary to the Shaw’s Creek restoration
+ Commence excavation, forming, placement of reinforcing steel for the new bridge abutment, East side

Picture
Picture
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.