An update from Serguei Kabanov, Project Manager at the Region of Peel
I would like to provide you with a quick update on the Phase 1 – Queen Street East construction: In the last two weeks, the Contractor: o Completed installation of ‘H’ piles for the new bridge abutments, East side o Completed pouring concrete for pre-cast arch culvert footing, West side o Commenced excavation, forming, placement of reinforcing steel and pouring concrete for pre-cast arch culvert footing, East side o Completed existing bridge removal o Completed installation of pre-cast arch culvert and commenced backfilling o Commenced excavation, forming, placement of reinforcing steel new bridge footing, East side o Commenced pouring new concrete curbs on the East side of the Creek o Commenced Tributary to Shaw’s Creek restoration In the next two weeks, the Contractor will: o Continue backfilling pre-cast arch culvert o Continue Tributary to Shaw’s Creek restoration o Complete the removal of existing bridge footings, both sides o Complete pouring concrete for the new bridge abutment, East side o Commence excavation for the new bridge abutment, West side o Commence installation of ‘H’ piles for the new bridge abutments, West side o Commence underground electrical works An update from Serguei Kabanov, Project Manager at the Region of Peel
This afternoon, the Contractor successfully installed pre-cast arch culvert over the Tributary to Shaw’s creek. An update from Serguei Kabanov, Project Manager at the Region of Peel
This morning, the Contractor successfully removed existing bridge over Shaw’s creek. An update from Serguei Kabanov, Project Manager at the Region of Peel
In the last two weeks, the Contractor: + Completed installation of ‘H’ piles for the new bridge abutments on the East side of the Creek + Completed pouring concrete for pre-cast arch culvert footing, West side + Completed the removal of existing concrete box culvert for Tributary to the Shaw’s Creek + Completed storm sewer installation on the West side of the Creek + Commenced excavation, forming, placement of reinforcing steel for pre-cast arch culvert footing, East side + Commenced pouring new concrete curbs on the East side of the Creek + Continued building proposed roadway on the East side of the Creek by placing limestone materials In the next two weeks, the Contractor will: + Continue pouring new concrete curbs on the East side of the Creek + Complete Tributary to the Shaw’s Creek restoration + Complete pouring concrete for pre-cast arch culvert footing, East side + Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek + Commence and complete Tributary to the Shaw’s Creek restoration + Commence excavation, forming, placement of reinforcing steel for the new bridge abutment, East side |
Categories
All
Archives
April 2023
|