Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

4/1/2019

0 Comments

 
In the last two weeks, the Contractor:
  • Installed eight digital portable variable message signs in the vicinity of Alton Village advising of upcoming construction
  • Installed four project sign boards
  • Installed 12 business guidance signs throughout the Village
  • Secured site trailer and compound facilities (located north of 14 Agnes Street)
  • Commenced removals throughout the project limits: trees

In the next two weeks, the Contractor:
April 11, 2019:
  • Will commence watermain installation on Main, between Station and Edmund (see sketch):
    • Existing Southbound lane will be temporary closed
    • Traffic will be diverted to Northbound lane and North-South direction will be controlled by temporary traffic signals
Picture
April 11, 2019:
  • Will commence road and boulevard removals along Queen Street East, from Phase 1 to Main/Queen Intersection (see sketch):
    • Existing Westbound lane will be temporary closed
    • Traffic will be diverted to Eastbound lane and East-West direction will be controlled by temporary traffic signals
Picture
*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
  • Phase 1:
    • Station to Edmund – COMPLETED
  • Phase 2:
    • Beechgrove to McClellan – ONGOING
    • McClellan to Station – upcoming
    • Edmund to Main/Queen Intersection – upcoming
    • McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
 
In the Event of an Emergency or Gas Shut Off, please contact the following Enbridge staff:
  • First call – Field inspector – Phil Sanderson – 416-998-0568
  • Second call – Escalation call, Management – Jeff Bruce – 416-819-3517
  • Emergency Dispatch – 1-833-872-3477
 
FOR YOUR INFORMATION:
  • Dufferin County will be completing road resurfacing and select culvert replacements on County Road 23, between Dufferin County Road 23 (B-Line) and Peel Regional Road 136 (Porterfield Road)
  • During construction of Phase 2, Canada Post relocated existing super boxes (mail boxes) from N/W corners of McClellan/Main and King/Main to Station Street, between Alton School and Library.  New mailboxes will be reinstalled to original location once construction is complete
Picture
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

3/19/2019

0 Comments

 
+ Staff finalized paperwork and executed the documents; project is awarded to Fermar Paving Limited
+ The Contractor is anticipated to mobilize on site Wednesday, March 20, 2019 and set up signage, barrels and a field office
+ Pre-Construction meeting will take place on Monday, March 25, 2019

The Contractor is anticipated to commence work on the new storm sewer and water-mains Tuesday, March 26, 2019:
- New storm sewer installation on Queen Street East, between railway tracks and Main Street and on Main Street South, between Queen Street East and McClellan Road
- Relocation of the water-main on Main Street South, between Station Street and Edmund Street


*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
Phase 1:
+ Station Street to Edmund Street – The new main and all service transfers will be completed by Friday, March 22, 2019; the old main along the West side of the Cemetery slope will be decommissioned and abandoned
Phase 2:
+ Station Street to McClellan Road – Work will commence on Monday, March 25, 2019
+ Main/Queen Intersection to Edmund Street – Work will commence in two weeks
+ McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
+ Beechgrove to McClellan – upcoming
March 26, 2019
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

3/1/2019

0 Comments

 
What are we doing?
+ Improving Main Street South and Queen Street East, including road reconstruction, drainage and boulevard improvements, providing on-street parking, decorative street lighting, streetscaping enhancements and landscaping.

The work includes, but is not limited to:
+ asphalt removal, road excavation and boulevard grading;
+ installation of new:
  • storm sewer
  • retaining wall structure at the cemetery with architectural finishes
  • vegetated retaining wall
  • barrier curbs
  • decorative coloured pattern concrete splash pads
  • wider concrete sidewalks
  • decorative architectural streetlighting
  • rest areas with street furniture
  • gateway features at South end (traffic calming measures); and
  • parkette area with town clock
+ pavement with wider lanes
+ improved pavement markings
l+ andscaping
+ minor related works; and,
+ Improvements to Caledon Fire Station 301 parking lot.


Where?
+ Main Street South, from Beechgrove Sideroad to Queen Street East
+ Queen Street East from Main Street South to East of Railway Tracks

​When?

+ Start: March, 2019
+ Finish: December 20, 2019, weather permitting
Picture
main_street_2019-03-01.pdf
File Size: 81 kb
File Type: pdf
Download File

0 Comments

​Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

2/26/2019

0 Comments

 
In the last month, the Region of Peel
+ Completed tendering processes and awarded Phase 2 works to Fermar Paving Limited http://www.fermarltd.com/
+ Staff are currently finalizing paperwork and executing the documents
+ The Contractor is anticipated to commence work mid to late March
​

*** Please note: Enbridge Gas Distribution retained NPL Canada https://nplcanada.ca/ to complete gas relocations in the Village. The contractor will be mobilizing the site this week, February 28/19, weather permitting. Work will commence in phases:
​

Phase 1:
+ Station Street to Edmund Street
Phase 2:
+ Main/Queen Intersection to Edmund Street
+ Station Street to McClellan Road

Work will include:
+ Relocation of gas mains and services along Main Street South, between Queen Street East and Beechgrove Sideroad
+ Relocation of gas substation from N/W to S/W corner of McClellan Road
0 Comments

Update on Queen Street East from the Region of Peel

2/4/2019

0 Comments

 

In the last two weeks, the Contractor:
+ Partially completed installation of bridge and culvert railings
+ Completed installation of gateway monument floodlight
 
*** Phase 2 – Alton Village Streetscaping project is currently in the tendering process with closing date of February 13, 2019.  Anticipated construction start date is mid-March, 2019 ***

0 Comments

Update on Queen Street East from the Region of Peel

7/24/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel
​

I would like to provide you with a quick update on the Phase 1 – Queen Street East construction:
In the last two weeks, the Contractor:
o Completed installation of ‘H’ piles for the new bridge abutments, East side
o Completed pouring concrete for pre-cast arch culvert footing, West side
o Commenced excavation, forming, placement of reinforcing steel and pouring concrete for pre-cast arch culvert footing, East side
o Completed existing bridge removal
o Completed installation of pre-cast arch culvert and commenced backfilling
o Commenced excavation, forming, placement of reinforcing steel new bridge footing, East side
o Commenced pouring new concrete curbs on the East side of the Creek
o Commenced Tributary to Shaw’s Creek restoration
​

In the next two weeks, the Contractor will:
o Continue backfilling pre-cast arch culvert
o Continue Tributary to Shaw’s Creek restoration
o Complete the removal of existing bridge footings, both sides
o Complete pouring concrete for the new bridge abutment, East side
o Commence excavation for the new bridge abutment, West side
o Commence installation of ‘H’ piles for the new bridge abutments, West side
o Commence underground electrical works
0 Comments

Update on Queen Street East from the Region of Peel

7/23/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel

This afternoon, the Contractor successfully installed pre-cast arch culvert over the Tributary to Shaw’s creek.

​
Picture
0 Comments

Update on Queen Street East from the Region of Peel

7/20/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel

This morning, the Contractor successfully removed existing bridge over Shaw’s creek.
0 Comments

Update on Queen Street East from the Region of Peel

7/10/2018

0 Comments

 
An update from Serguei Kabanov, Project Manager at the Region of Peel
 
In the last two weeks, the Contractor:
+ Completed installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
+ Completed pouring concrete for pre-cast arch culvert footing, West side
+ Completed the removal of existing concrete box culvert for Tributary to the Shaw’s Creek
+ Completed storm sewer installation on the West side of the Creek
+ Commenced excavation, forming, placement of reinforcing steel for pre-cast arch culvert footing, East side
+ Commenced pouring new concrete curbs on the East side of the Creek
+ Continued building proposed roadway on the East side of the Creek by placing limestone materials
In the next two weeks, the Contractor will:
+ Continue pouring new concrete curbs on the East side of the Creek
+ Complete Tributary to the Shaw’s Creek restoration
+ Complete pouring concrete for pre-cast arch culvert footing, East side
+ Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek
+ Commence and complete Tributary to the Shaw’s Creek restoration
+ Commence excavation, forming, placement of reinforcing steel for the new bridge abutment, East side

Picture
Picture
0 Comments

The Region of Peel are asking for help

6/29/2018

0 Comments

 
Region of Peel have been reporting minor vandalism at the Queen Street East bridge construction site and have asked us to help keep watch.
This type of activity is very destructive. We want to keep our community safe, so we're asking all neighbours to help keep an eye out for this type of activity and to please report it immediately to the O.P.P. Thank you.
Picture
0 Comments

Queen Street East update from the Region of Peel

6/26/2018

0 Comments

 
An update from Serguei Kabanov of the Region of Peel
  • In the last two weeks, the Contractor:
    • Completed temporary diversion of Tributary to the Shaw’s Creek through temporary by-pass culvert
    • Completed concrete retaining wall (toe wall) on the South side of Queen Street, West of the railway tracks
    • Commenced excavation, framing and placement of reinforcing steel for pre-cast arch culvert footing, West side
    • Continued installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
    • Continued building proposed roadway on the East side of the Creek by placing limestone materials
    • Continued installation of new storm sewer, throughout
  • In the next two weeks, the Contractor will:
    • Continue building proposed roadway on the East side of the Creek
    • Complete storm sewer installation on the West side of the Creek
    • Complete pouring concrete for pre-cast arch culvert footing, West side
    • Complete the removal of existing concrete box culvert for Tributary to the Shaw’s Creek
    • Complete installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
    • Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek
    • Commence Tributary to the Shaw’s Creek restoration


0 Comments

Info from the Region of Peel - Public Information Meeting June 6, 2018

6/12/2018

0 Comments

 
On June 6th, 2018 the Region of Peel hosted a public information meeting to update the community on the Alton Village Streetscaping project at the Alton Public School. Serguei Kabanov, the project manager, has sent us this file of the images that were on display to share with the community.
region_of_peel_2018-06-12.pdf
File Size: 6104 kb
File Type: pdf
Download File

0 Comments

Queens Street East Update from the Region of Peel

6/12/2018

0 Comments

 
An update from Serguei Kabanov of the Region of Peel
  • In the last two weeks, the Contractor:
    • Completed storm sewer installation on the East side of the Creek
    • Completed installation of temporary by-pass culvert for the Tributary to the Shaw’s Creek
    • Commenced storm sewer installation on the West side of the Creek
    • Commenced installation of concrete retaining wall on the South side of Queen Street, West of the railway tracks
    • Commenced cutting/filling for the proposed roadway on the East side of the Creek
    • Continue installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
  • In the next two weeks, the Contractor will:
    • Continue building proposed roadway on the East side of the Creek
    • Complete storm sewer installation on the West side of the Creek
    • Complete concrete retaining wall on the South side of Queen Street, West of the railway tracks
    • Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek
    • Commence the removal of the existing concrete box culvert at the Tributary to the Shaw’s Creek and form new footings
Picture
0 Comments

Main Street Streetscaping info re: Low-Impact Development (LID) Storage Tanks

6/1/2018

0 Comments

 
The Alton Village Association recently asked Serguei Kabanov (of the Region of Peel) to describe Low Impact Development underground storage tanks are, and explain "Lay By" (as per the Main Street Streetscaping plan)here is what he shared:

Lay-by is on-street parking which will be provided on the South side of Queen Street East, between Alton Grange Trail entrance and the new bridge
  • It will accommodate a total of 8 vehicles (2 accessible spots)
  • Surface of the lay-by area will be made out of large permeable stone
​LID underground storage tanks - Stormtec will be positioned below the lay-by surface area
  • The tanks are plastic storage tanks (dome shape pipes, see below) installed under the road to collect and retain any water runoff and gradually infiltrate into the ground, rather than discharge into the Creek
  • Oil Grid Separators (OGS) will be installed to treat any run-off prior to discharging it to the underground storage tanks
Picture
Picture
0 Comments

Queens Street East Update from the Region of Peel

5/31/2018

0 Comments

 
 Update on the Phase 1 
Queen Street East construction: May 31, 2018
From Serguei Kabanov, Project Manager
​
  • In the last two weeks, the Contractor:
    • Commenced installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
    • Commenced and completed installation of Low-Impact-Development (LID) underground storage tanks for the proposed lay-by area
    • Continued placement of new granular material for the road base in the East end of the project
  • In the next two weeks, the Contractor:
    • Will continue installation of ‘H’ piles for the new bridge abutments
    • Will commence storm sewer installation
    • Will commence preliminary work for the Tributary to the Shaw’s Creek by-pass​
Picture
Picture
0 Comments

Region of Peel - Public Meeting

5/22/2018

0 Comments

 
Picture
This is the Public Information Centre #3 to present proposed improvements to Main Street South / Queen Street East (Regional Road 136).

Phase 2: Improvements to Main Street South / Queen Street East include road reconstruction, intersection reconfiguration, new retaining walls, drainage improvements, provision for on-street parking, decorative streetlighting, boulevard improvements, and streetscaping enhancements.

For project details, call: Serguei Kabanov
905-791-7800, EXT. 8754
Picture
0 Comments

Queen Street East Update from the Region of Peel

5/15/2018

0 Comments

 
From Serguei Kabanov, Project Manager
​

In the last two weeks:
- The Contractor completed installation of sheet piles at Shaw's Creek and excavation and removal of peat material underneath the existing roadway in the vicinity of the Creek.
- The Contractor commenced placement of new granular material for the road base
In the next two weeks:
- The Contractor will commence installation of ‘H’ piles for the new bridge abutments and continue earth works.
Picture
0 Comments

Queen Street East Update from the Region of Peel

5/2/2018

0 Comments

 
From Serguei Kabanov, Project Manager

We would like to provide you with a quick update on the Phase 1 – Queen Street East construction:

In the last two weeks:

• The Contractor commenced installation of sheet piles at Shaws Creek and continued with the excavation and removal of peat material underneath the existing roadway in the vicinity of the CreeIn the next two weeks:

• The Contractor will continue and complete excavation and removal of peat material underneath the existing roadway in the vicinity of the Creek and commence excavation for the new bridge footings.
Serguei Kabanov, Project Manager, will continue to provide updates with major milestones and highlights of the project.
Once again, should anyone have any questions, please contact him at 905-791-7800 ext. 8754 or serguei.kabanov@peelregion.ca.
Thank you
Picture
0 Comments

Queen Street East Update from the Region of Peel

4/18/2018

0 Comments

 
From Serguei Kabanov, Project Manager
 
We would like to provide you with a quick update on the Phase 1 – Queen Street East construction:
 
  • Due to wet weather and unexpected snow, our construction activities are paused.  We anticipate to resume work by the end of the week.
  • Our Contractor cleared all residential driveways located within the construction closure and affected by the weather and ensured residents can safely enter/exit their properties
  • In the last two weeks:
    • The Contractor commenced excavation and grading operations in the east end of the project.
  • In the next two weeks:
    • The Contractor will concentrate on excavation and removal of peat material underneath the existing roadway.
    • In addition, our Contractor will commence sampling residential wells, building inspection surveys for residential properties and vibration monitoring in the vicinity of the project limits
Picture
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.