Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

3/19/2019

0 Comments

 
+ Staff finalized paperwork and executed the documents; project is awarded to Fermar Paving Limited
+ The Contractor is anticipated to mobilize on site Wednesday, March 20, 2019 and set up signage, barrels and a field office
+ Pre-Construction meeting will take place on Monday, March 25, 2019

The Contractor is anticipated to commence work on the new storm sewer and water-mains Tuesday, March 26, 2019:
- New storm sewer installation on Queen Street East, between railway tracks and Main Street and on Main Street South, between Queen Street East and McClellan Road
- Relocation of the water-main on Main Street South, between Station Street and Edmund Street


*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
Phase 1:
+ Station Street to Edmund Street – The new main and all service transfers will be completed by Friday, March 22, 2019; the old main along the West side of the Cemetery slope will be decommissioned and abandoned
Phase 2:
+ Station Street to McClellan Road – Work will commence on Monday, March 25, 2019
+ Main/Queen Intersection to Edmund Street – Work will commence in two weeks
+ McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
+ Beechgrove to McClellan – upcoming
March 26, 2019
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

3/1/2019

0 Comments

 
What are we doing?
+ Improving Main Street South and Queen Street East, including road reconstruction, drainage and boulevard improvements, providing on-street parking, decorative street lighting, streetscaping enhancements and landscaping.

The work includes, but is not limited to:
+ asphalt removal, road excavation and boulevard grading;
+ installation of new:
  • storm sewer
  • retaining wall structure at the cemetery with architectural finishes
  • vegetated retaining wall
  • barrier curbs
  • decorative coloured pattern concrete splash pads
  • wider concrete sidewalks
  • decorative architectural streetlighting
  • rest areas with street furniture
  • gateway features at South end (traffic calming measures); and
  • parkette area with town clock
+ pavement with wider lanes
+ improved pavement markings
l+ andscaping
+ minor related works; and,
+ Improvements to Caledon Fire Station 301 parking lot.


Where?
+ Main Street South, from Beechgrove Sideroad to Queen Street East
+ Queen Street East from Main Street South to East of Railway Tracks

​When?

+ Start: March, 2019
+ Finish: December 20, 2019, weather permitting
Picture
main_street_2019-03-01.pdf
File Size: 81 kb
File Type: pdf
Download File

0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.