Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

5/29/2019

0 Comments

 
 The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – North side of the roadway remains temporary closed – signals in place. Main Street South, between King and Station – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
 In the last two weeks, the Contractor:
  • Completed storm sewer installation along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed installation of new watermain services on the West side of Main Street South, between King and Station
  • Continued road excavation and granular placement along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Continued installation of vegetated retaining wall along the North side of Queen Street East, West of the train tracks
  • Continued installation of crane platform – fill at cemetery slope, between , between King and Station
  
In the next two weeks, the Contractor will:
  • Complete decommissioning – plugging of existing watermain between Station and King, including the removal of hydrant
  • Complete installation of crane platform – fill at cemetery slope, between , between King and Station
  • Continue and complete installation of vegetated retaining wall along the North side of Queen Street East, West of the train tracks
  • Continue and complete road excavation and granular placement along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Commence and complete relocation of the school flashing beacon at the cemetery further to the north, away from crane pad – fill
  • Commence storm sewer installation at Main/Queen Intersection
  • Commence road excavation at Main/Queen Intersection (some lanes at the intersection may be left on gravel for a short duration)
  • Commence storm sewer installation along the West side of Main Street South, from Main/Queen Intersection to King
  • Commence road excavation along the West side of Main Street South, from Main/Queen Intersection to King
  • Commence placement of concrete curb along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Commence installation of the retaining wall at the cemetery
  • Commence underground electrical work along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  •  
 
*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
 
 
Phase 1:
Station to Edmund – COMPLETED
 
 
Phase 2:
Edmund to Main/Queen Intersection – COMPLETED
Station to McClellan – COMPLETED
McClellan (Main to Agnes) – COMPLETED
McClellan to Beechgrove – COMPLETED
McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming

Picture
Picture
Picture
0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

5/29/2019

0 Comments

 
The roadway remains open, with temporary lane closures between 07:00AM and 5:00PM, Monday to Friday.
  • In the last two weeks, the Contractor:
    • Completed placement of top soil/seed – terraseeding, throughout
    • Completed general parging and sealing a the bridge and culvert structures
    • Completed general site clean-up
 
  • In the next two weeks, the Contractor:
    • Will commence and complete final driveway restoration and roadway base asphalt repairs, throughout (repairs to the asphalt at the railway tracks is scheduled for May 30-31)
    • Will commence and complete installation of decorative patterned colour concrete splash pads (area between the back of curb and front of sidewalk), throughout
    • Will commence and complete additional planting at the gateway monument
    • Will commence and complete installation of black ‘ALTON’ letters at the gateway monument
Picture
0 Comments

Annual General Meeting

5/9/2019

0 Comments

 
Picture
Location: Paul Morin Gallery – 19741 Main Street Alton
Date: Tuesday, June 6, 2019
Time: 7:00 p.m.

Agenda

 + Short Business Meeting  
+ Alton Trivia – fun questions on the History of Alton
​
by Jane Ansara
+ Neighbourhood Watch, and Protecting your Property
by Jane Ansara and the Caledon O.P.P.

Please join or renew your annual Alton Village Association 2019 membership. For only $10.00 a year, you can belong to the AVA
See event calendar
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.