Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

10/30/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between Queen and Station – East side of the roadway remains temporary closed – signals in place, and Main Street South, between McClellan and 360m South – East side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM.
 
* Please note that we will be commencing reconstruction of McClellan Road, from Main to Agnes on Monday, November 4, 2019.  Road excavation and granular placement will commence at Main Street and progress to the West.  It is anticipated to complete all excavation and granular placement within 5-6 days.  All trucks with new granular (long larger trucks) will be arriving to McClellan from Main Street and backing into.  All trucks with excavated material (shorter smaller trucks) will be leaving through McClellan-Agnes-King-Main.  In preparation for road excavation on Monday, McClellan road will be milled and placed on gravel this coming Friday, November 1, 2019.  All entrances will be ramped and proper signage will be placed.  Starting Monday, November 4, 2019, McClellan Road will be closed to through traffic between 08:00AM and 5:00PM.  During those hours, access to the West part of Alton Village shall be through King-Agnes.  Emergency access will be provided.
 
In the last two weeks, the Contractor:
+ Completed placement of base asphalt along the East side of Main Street South, between McClellan and North of Station
+ Completed installation of storm sewer and underground infiltration chambers along the East side of Main Street South, between Edmund and North of Station
+ Completed construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed installation of decorative fences installations on Queen Street East, from train tracks to East of Main/Queen Intersection
+ Completed tree planting on Queen Street East, from train tracks to East of Main/Queen Intersection and on Main Street, from Beechgrove to 360m South of McClellan
+ Completed placement of top soil on Queen Street East, from train tracks to East of Main/Queen Intersection and on Main Street, from Beechgrove to McClellan
+ Completed placement of sod at the Fire Hall and on Queen Street East, from train tracks to East of Main/Queen Intersection
+ Completed road excavation and granular placement along the East side of Main Street South, between Queen and North of Station
+ Continued installation of decorative streetlight poles and pulling underground cables, throughout
+ Continued work on parkette area at S/E corner of Main/Queen Intersection
+ Commenced installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Commenced installation of armour stone at Northerly gateway island
+ Commenced construction of amenity/rest area in front of the old school
 
In the next two weeks, the Contractor:
+ Complete asphalt removal, road excavation and granular placement on McClellan, between Main and Agnes (see ‘*’ above)
+ Complete installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Complete installation of lattice fence installation at the gas station
+ Complete installation of chain link fence on Queen Street East
+ Complete installation of permeable pavers at lay-by on Queen Street East
+ Complete installation of permeable pavers at parkette area at S/E corner of Main/Queen Intersection
+ Commence installation of storm sewer on McClellan, between Main and Agnes
+ Commence placement of concrete curbs along the East side of Main Street South, between Queen and North of Station
+ Commence road excavation along the East side of Main Street South, between McClellan and 260m to South
+ Commence installation of patterned concrete colour splash pads on Queen Street East, from train tracks to East of Main/Queen Intersection
+ Commence placement of concrete sidewalks, throughout
+ Continue work on gateway islands on Main Street, North of Beechgrove
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

10/18/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between Queen and McClellan – East side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM.
 
Please note that 2 Pay Duty Officers will be present on Monday, October 21st, from 09:30AM to 9:30PM at Station and Edmund Intersections on Main Street South to assist with traffic control due to Federal Election.
 
In the last two weeks, the Contractor:
+ Completed installation of storm sewer along the East side of Main Street South, between Queen and Edmund
+ Completed placement of concrete curbs along the East side of Main Street South, between North of Station and McClellan
+ Completed placement of concrete sidewalks along the East side of Main Street South, between Station and McClellan
+ Continued installation of decorative streetlight poles and pulling underground cables, throughout
+ Commenced installation of storm sewer and underground infiltration chambers along the East side of Main Street South, between Edmund and North of Station
+ Commenced construction of parkette area at S/E corner of Main/Queen Intersection
 
In the next two weeks, the Contractor will:
+ Complete placement of base asphalt along the East side of Main Street South, between North of Station and McClellan
+ Complete installation of storm sewer and underground infiltration chambers along the East side of Main Street South, between Edmund and North of Station
+ Complete construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Complete construction of parkette area at S/E corner of Main/Queen Intersection
+ Complete installation of lattice fence installation at the gas station
+ Complete installation of chain link and decorative fences installations on Queen
+ Complete tree planting on Queen Street East, from train tracks to East of Main/Queen Intersection and on Main Street, from Beechgrove to McClellan
+ Complete placement of top soil
+ Commence forming retaining wall at the cemetery
+ Commence road excavation and granular placement along the East side of Main Street South, between Queen and North of Station
+ Commence installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Commence placement of concrete sidewalks along the West side of Main Street South, between Station and McClellan
+ Commence work on gateway islands on Main Street, North of Beechgrove

0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 1 from Serguei Kabanov, Project Manager

10/2/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between Queen and McClellan – East side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
  • Please note that all fire trucks at Caledon Fire Station 301 are back at the station
  • Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
  • Please note that construction activities are ongoing around the school frontage.  All entrances are open during morning/afternoon rush hours.
 
In the last two weeks, the Contractor:
+ Completed construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Completed asphalt removal, curb and sidewalk along the East side of Main Street South, between Queen and Station
+ Completed road excavation and granular placement along the East side of Main Street South, between Station and McClellan
+ Completed placement of base and top asphalt at Fire Hall parking lot
+ Continued underground electrical works, throughout
+ Continued driveway reconstruction along the West side of Main Street South, between King and McClellan
+ Commenced installation of lattice fence installation at the gas station
+ Commenced installation of chain link and decorative fences installations on Queen
+ Commenced installation of decorative streetlight poles and luminaires on Queen and Main
+ Commenced installation of storm sewer along the East side of Main Street South, between Queen and Station
+ Commenced construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
 
In the next two weeks, the Contractor will:
+ Complete installation of storm sewer along the East side of Main Street South, between Queen and Edmund
+ Complete construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Complete installation of lattice fence installation at the gas station
+ Complete installation of chain link and decorative fences installations on Queen
+ Complete placement of concrete curbs along the East side of Main Street South, between North of Station and McClellan
+ Continue underground electrical works, throughout
+ Commence placement of sidewalks along the East and West sides of Main Street South, between Station and McClellan
+ Commence forming retaining wall at the cemetery
+ Commence installation of storm sewer along the East side of Main Street South, between Edmund and Station
+ Commence road excavation and granular placement along the East side of Main Street South, between Queen and Edmund
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 1 from Serguei Kabanov, Project Manager

10/2/2019

0 Comments

 
In the last two weeks, the Contractor:
+ Completed re-grading of boulevard gravel shoulders
+ Completed replacement of guide rails
 
In the next two weeks, the Contractor will:
+ Complete replacement and planting of new shrubs/trees

Picture
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.