Update on Phase 1 &2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

6/26/2019

0 Comments

 
The roadway is open.

In the last two weeks, the Contractor:
  • Completed final driveway restoration and roadway base asphalt repairs, throughout
  • Completed installation of decorative patterned colour concrete splash pads (area between the back of curb and front of sidewalk), throughout
  • Completed power washing and sealing decorative patterned colour concrete splash pads, throughout
  • Completed installation of black ‘ALTON’ letters at the gateway monument
  • Completed placement of top asphalt
  • Commenced placement of new thermoplastic pavement markings
  • In the next two weeks, the Contractor:
  • Will complete placement of new thermoplastic pavement markings
  • Will commence additional planting at the gateway monument
  • General site clean-up

PHASE 2:
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place. Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.

*** What is Happening at the Cemetery side slope, along Main Street?
We continue to construct brand new reinforced concrete retaining wall along the West side of Main Street, fronting Alton Cemetery. The wall is constructed in the flowing stages:
  • Utility relocations: Enbridge and watermain – COMPLETED
  • Temporary closure of Southbound lane and installation of temporary concrete barriers – COMPLETED
  • Placement of temporary ‘fill’ material or cut-off-level (limestone granular material) in order to create safe and stable working platform for the crane – COMPLETED
  • Tree branches clearance/support: the branches for the main tree at the cemetery were tied back – COMPLETED
  • Equipment and material: mobilize crane and drilling equipment – COMPLETED
  • Drilling/Concrete – CONTINUED
  • * 1m in Diameter holes will be drilled side-by-side along the top portion of the slope at various depths
  • Holes will be reinforced with steel I-beams and filled with concrete – caissons
  • Removal of temporary ‘fill’ material or cut-off-level – UPCOMING
  • Excavation of earth slope in front of caissons – UPCOMING
  • Installation of decorative reinforced face to mimic historic church on the East side – UPCOMING

In the last two weeks, the Contractor:
  • Completed installation of low impact development on-street parking on the North side of Queen Street East, West of the tracks
  • Completed storm sewer installation at Main/Queen Intersection (moving southerly)
  • Completed placement of concrete curb along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed installation of sidewalk along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed placement of base asphalt along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection – traffic is switched onto the new road
  • Completed the removal of existing asphalt, curbs and sidewalk along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed the removal of existing asphalt at Main/Queen Intersection
  • Continued installation of the retaining wall at the cemetery
  • Continued underground electrical works, throughout
  • Continued storm sewer installation South of Main/Queen Intersection

In the next two weeks, the Contractor will:
  • Complete road excavation at Main/Queen Intersection
  • Complete placement of concrete curbs and sidewalks at Main/Queen Intersection
  • Complete placement of base asphalt at Main/Queen Intersection
  • Continue installation of the retaining wall at the cemetery
  • Continue storm sewer installation along the West side of Main Street South, from Main/Queen Intersection to McClellan
  • Continue road excavation along the West side of Main Street South, from Main/Queen Intersection to McClellan
  • Commence storm sewer installation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection

*** Please note Enbridge Gas Distribution (NPL Canada) completed all gas relocations in the Village ***

Picture
Picture
Picture
Picture
Picture
Picture
Picture
Picture
0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

6/20/2019

0 Comments

 
Queen Street East will be closed to through traffic from Main/Queen Intersection to Queen/Porterfield Intersection.  Monday, June 24, between 07:00AM and 5:00PM, weather permitting.

PHASE 1:
As per the previous UPDATE #40, our Contractor will be completing placement of top asphalt and new thermoplastic pavement markings on Monday, June 24, between 07:00AM and 5:00PM, weather permitting.

As such, Queen Street East will be closed to through traffic from Main/Queen Intersection to Queen/Porterfield Intersection.

We will be notifying all emergency services. Local traffic, West of the railway tracks, can entire/exit from the West only. Local traffic, East of railway tracks, will have limited access to properties due to paving operations and encouraged to vacate driveways (if needed) prior to 07:00 AM. OPP Pay Duty Police Officers will be on site to assist with traffic control and roadway closures.

We will be bringing in additional equipment and manpower to complete this work as quickly as possible. We greatly appreciate your cooperation in this matter.

I will continue to provide updates with major milestones and highlights for both Phases of the project.

Once again, should you have any questions, please contact me at

905-791-7800 ext. 8754 or serguei.kabanov@peelregion.ca.

Serguei Kabanov, CD, CET, rcca
Project Manager Roads – Design and Construction Public Works
10 Peel Centre Drive Suite ‘B’, 4th Floor
Brampton, Ontario
L6T 4B9
Tel: 905-791-7800 ext. 8754
Cell: 416-902-7425
Serguei.kabanov@peelregion.ca


Picture
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.