As per previous Update #60, in the next week, our Contractor will be completing major paving operations in the Village of Alton. The following works are scheduled to take place June 22-26 week, weather dependent:
Monday June 22:
King Street, Edmund Street, Station Street, McClellan Road
+ Placement of top asphalt
+ Temporary road closures are anticipated
Tuesday June 23 – Friday June 26:
Main Street South, from Main/Queen Intersection to 800m South of Beechgrove Sideroad
Tuesday June 23: Placement of top asphalt
+ No road closure is anticipated; lane reductions in effect – single lane; pay duty police assisting with traffic control
Wednesday June 24: Placement of top asphalt
+ No road closure is anticipated; lane reductions in effect – single lane; pay duty police assisting with traffic control
Wednesday June 24 - Friday June 26:
+ Placement of permanent pavement markings (Queen St E, Main St S, King St, Edmund St, Station St, McClellan Rd)
Thursday June 25 – Friday June 26:
Main/Queen Intersection, School Crossing, Fire Fall
+ Application of pattern colour asphalt crosswalks and warning areas