Update from the Region of Peel on Alton Village Streetscaping from Serguei Kabanov, Project Manager

4/29/2020

0 Comments

 

The roadway remains open with temporary lane closures:
+ Main Street South, North of Beechgrove (around the Southern island) – East side of the roadway remains temporary closed – signals in place; and,
+ Main Street South, between South of Alton Greenhouses and McClellan Road – West side of the roadway remains temporary closed – signals in place.
+ Main Street South, between Station and South of King (at cemetery slope) – West side of the roadway remains temporary closed – signals in place;
In the last two weeks, the Contractor:
o Completed the repairs to the damaged streetlight pole on Phase 1, East of Bridge
o Completed installation of armour stone flower bed at S/W corner of Main and Queen, South of Headwaters Plastic Surgery
o Completed grading, forming and pouring concrete sidewalk along the East side of Main Street, from McClellan to South
o Completed grading, forming and pouring concrete sidewalk along the West side of Main Street, around Alton Greenhouses
o Completed installation of armour stone retaining wall at #19605 Main Street
o Completed forming and pouring final two 10m long sections (#7 and #8) for the retaining wall adjacent to the cemetery
o Continued grading and forming for concrete sidewalk along the West side of Main Street, South of McClellan
o Continued placement of armour stone at median island, North of Beechgrove
o Continued driveways reconstruction
o Commenced masonry work at Gateway monument, on Main Street
o Commenced grading and forming for concrete sidewalk along the North side of McClellan, between Main and Agnes
o Commenced installation of permeable pavers at on-street lay-bys along the West side of Main Street, South of McClellan
o Commenced installation of rest area/Canada Post pad on Main Street, South of McClellan
In the next two weeks, the Contractor will:
o Complete placement of armour stone at median island, North of Beechgrove
o Complete masonry work at Gateway monument, on Main Street
o Complete grading, forming and pouring concrete sidewalk along the North side of McClellan, between Main and Agnes an don Main Street, South of McClellan
o Complete installation of permeable pavers at on-street lay-bys along the West side of Main Street, South of McClellan
o Continue adjustments and repairs to curbs and sidewalks
o Commence and complete backfilling the retaining wall adjacent to the cemetery
o Commence and complete grading, forming and pouring concrete sidewalk along the retaining wall adjacent to the cemetery
o Commence stone work at the retaining wall adjacent to the cemetery
o Commence curbs, walkways and flower beds at the parkette area

0 Comments

Update from the Region of Peel on Alton Village Streetscaping from Serguei Kabanov, Project Manage

4/14/2020

0 Comments

 
Phase 2
The roadway remains open with temporary lane closures:
• Main Street South, between Station and South of King (at cemetery slope) – West side of the roadway remains temporary closed – signals in place; and,
• Main Street South, North of Beechgrove (around the Southern island) – East side of the roadway remains temporary closed – signals in place.

*** Please note that our Contractors are actively working on the remaining items:
• Since the last update, the Contractor:
• Continued work on the retaining wall adjacent to the cemetery:
• Installed steel reinforcement: drilled-in dowels, vertical and horizontal bars
• Formed and poured four 10m sections (#2, #4, #5 and #6)
• Continued forming final two 10m long sections (#7 and #8) – final concrete pour is scheduled for the last week of April
• Commence placement of armour stone blocks at Southern gateway island, North of Beechgrove
• Commenced stone work at gateway monument at Northern island, North of Beechgrove
• Commenced removal and placement of granular material for new sidewalks and decorative splash pads along both East and West sides of Main Street, South of McClellan
• Commenced driveways reconstruction

Just as a reminder, once all sections (eight in total) of the concrete wall at the cemetery are poured, random stones will be installed inside the wall formed openings. The back side of the wall will be backfilled and a swale for drainage provided. Black aluminum railing will be installed on top of the wall, throughout the entire length.
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.