Update on Queen Street East from the Region of Peel

10/17/2018

0 Comments

 
Update on Phase 1 
Queen Street East construction Oct 17, 2018
from Serguei Kabanov, Project Manager

In the last two weeks, the Contractor:
+ Completed framing underside of the new bridge
+ Completed installation of remaining vegetated retaining walls
+ Completed installation of remaining storm sewer 
+ Completed terraseeding slopes and ditches at the East Limit and hydroseeding vegetated retaining wall
+ Commenced placement of structural steel for the new bridge beck
+ Commenced forming parapet walls and posts for the new culvert
+ Continued installation of decorative streetlight poles and underground, throughout
+ Continued placement of curbs and sidewalks, throughout
+ Continued road excavation and granular placement at the West Limit
​

In the next two weeks, the Contractor will:
+ Complete hydroseeding remaining vegetated retaining wall
+ Complete forming and pouring concrete for parapet walls and posts for the new culvert
+ Complete placement of structural steel for the new bridge beck
+ Continue granular placement at the West Limit
+ Continue placement of curbs and sidewalks, throughout
+ Continue installation of decorative streetlight poles and underground wire, throughout
+ Commence placement of base asphalt for the roadway
+ Commence placement of permeable paver stones at lay-by parking
+ Commence construction of rest areas, throughout
0 Comments

Alton Firefighters Pancake Breakfast

10/15/2018

0 Comments

 
Station 301 Alton Fire Hall - Open House Pancake Breakfast served by your Firefighters. Enjoy a pancake breakfast & meet your local firefighters. 

Picture
0 Comments

Update: Shaws Creek Road Culvert Replacement

10/5/2018

0 Comments

 
Update

Due to contractor material procurement delays, the road closure for Shaws Creek Road Culvert Replacement Project will be extended to: Friday, October 26, 2018
​

Staff are committed to finishing the project as quickly as possible and appreciate the cooperation of local residents.
0 Comments

Election

10/5/2018

0 Comments

 
Hi everyone the Alton Village Association want to remind you that the 2018 Municipal Election is quickly approaching. We encouraging everyone to vote. Remember your vote counts.

DATE/TIME/LOCATION(S)

ADVANCED VOTING
Saturday, Oct. 6th, 10:00 a.m. to 3:00 p.m.
Saturday, Oct. 13th, 10:00 a.m. to 3:00 p.m.
Thursday Oct.18th, 12:00 p.m. to 8:00 p.m.
Friday Oct. 19th, 12:00 p.m. to 8:00 p.m.

Caledon Central Public School
18357 Kennedy Rd.


ELECTION DAY
MONDAY, Oct. 22, 10:00 a.m. to 8:00 p.m.

Alton Public Library
35 Station Street

Caledon Central Public School
18357 Kennedy Rd.

Inglewood Community Centre
15825 McLaughlin Road
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.