+ Completed installation of decorative railing at toe wall and rest area
+ Completed pouring concrete for parapet walls and posts for the new bridge
+ Completed bridge deck waterproofing
+ Completed placement of base asphalt on the new bridge
+ Commenced installation of guide rail and chain link fence
In the next two weeks, the Contractor:
+ Complete installation of guide rail and chain link fence
+ Complete installation of luminaires, decorative pedestrian streetlight mast arms, banner arms and flower pot holders, throughout
+ Complete installation of signage
+ Complete temporary line painting/markings
+ Complete installation of bridge and culvert railings
+ Continue gateway monument construction
+ Open the road
At this time, we are tentatively scheduling to open the roadway on Wednesday, December 19, 2018.