Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

11/27/2019

0 Comments

 
​The roadway remains open, with temporary lane closures: Main Street South, between Queen and Station – West side of the roadway remains temporary closed – signals in place, and Main Street South, between McClellan and 360m South – West side of the roadway remains temporary closed – signals in place.  McClellan Road, from Main to Agnes continues to be closed during the day – detour in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM.
 
In the last two weeks, the Contractor:
  • Completed installation of storm sewer on McClellan, between Main and Agnes
  • Completed road excavation and placement of granular material on McClellan, between Main and Agnes
  • Completed placement of concrete curbs on McClellan, between Main and Agnes
  • Completed installation of underground streetlighting conduits and cables on McClellan, between Main and Agnes
  • Completed road excavation and placement of granular material along the East side of Main Street South, between McClellan and 260m to South
  • Completed placement of base asphalt along the East side of Main Street South, between Queen and North of Station
  • Completed placement of top asphalt on Queen Street East/West/Intersection from train tracks to Main/Queen Intersection
  • Completed placement of concrete sidewalks along the East side of Main Street South, between Main/Queen Intersection and North of Station
  • Completed placement of concrete sidewalks along the West side of Main Street South, between McClellan and the Cemetery
  • Completed pouring concrete footing, the base and the column for the gateway monument on Main Street at Northerly island
  • Completed sealing all pattern colour concrete splash pads on Queen Street, between train tracks and Main/Queen Intersection
  • Completed placement of top asphalt for driveways on Queen Street, between train tracks and Main/Queen Intersection
  • Commenced installation of storm sewer along the West side of Main Street South, between McClellan and 260m to South
  • Commenced road excavation and placement of granular material along the West side of Main Street South, between McClellan and 260m to South
  • Commenced placement of permeable pavers at lay-bys on Main Street, between Station and Main/Queen Intersection
 
In the next two weeks, the Contractor:
  • Complete storm sewer installation along the West side of Main Street South, between McClellan and 260m to South
  • Complete road excavation and placement of granular material along the West side of Main Street South, between McClellan and 260m to South
  • Complete placement of concrete curbs along the East and West sides of Main Street South, between McClellan and 260m to South
  • Complete placement of base asphalt on Main Street South, between McClellan and 260m to South
  • Complete placement of base asphalt on McClellan, between Main and Agnes
  • Complete installation of streetlighting poles on McClellan, between Main and Agnes
  • Complete placement of concrete sidewalks along the West side of Main Street South, between the Cemetery and King Street
  • Complete installation of armour stone at Northerly gateway island
  • Complete installation of permeable pavers at all lay-bys, throughout
  • Complete installation of street furniture and waste bins at amenity areas, throughout
  • Complete installation of guide rail at N/E corner of Main/Queen Intersection
  • Continue work on gateway monument and armour stone at Southerly gateway island
  • Commence forming retaining wall at the cemetery
0 Comments

Annual Lighting of the Tree

11/26/2019

0 Comments

 
Picture
Please join the Alton Village Association (AVA) for our
Annual Alton Village Square Christmas Tree Lighting

At the Alton Village Square

Saturday, Dec. 14th. 2019    
5:00 p.m. to 7:00 p.m.

 
Hear our Town Crier, Meet Santa, Sing Christmas Carols
Enjoy Free Hot Cider
 Hot Dogs   $2.00 each
S’mores     $1.00 each
 
50/50 Draw - Tickets $2.00 each or 3 for $5.00
Cookie Donations Are Welcomed
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

11/18/2019

0 Comments

 
As per the previous update (on Nov-13), top asphalt will be placed on Queen Street East/West, from train tracks to and including Main/Queen Intersection, on Wednesday, November 20, 2019. During paving operations, Queen Street East will be closed with temporary detour in place and pay duty police. Some temporary traffic interruptions will be necessary around Main/Queen Intersection.
​

Full temporary roadway closure/paving operations will commence around 09:00AM, after all preparatory work around train tracks is complete and residential driveways on Queen Street East are paved. The Region kindly requests that all residents and businesses travelling through this area on Wednesday, exercise caution and be patient. If possible, please avoid the area.
Picture
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

11/13/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between Queen and Station – East side of the roadway remains temporary closed – signals in place, and Main Street South, between McClellan and 360m South – East side of the roadway remains temporary closed – signals in place.  McClellan Road, from Main to Agnes continues to be closed during the day – detour in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM.
 
* Please note that we are tentatively scheduling placement of top asphalt and permanent line painting on Queen Street East, from Main/Queen Intersection to train tracks for the upcoming Wednesday, November 20, 2019, weather dependent.  The work will commence at the train tracks and progress Westerly.  During that work, Queen Street East will be temporary closed with detour and Pay Duty Officers in place.  Further update on the closure will be provided on Monday, November 18, 2019.
 
In the last two weeks, the Contractor:
+ Completed asphalt removal, road excavation and granular placement on McClellan, between Main and Agnes
+ Completed installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Completed installation of lattice fence installation at the gas station
+ Completed installation of chain link fence on Queen Street East, West of the tracks
+ Completed installation of permeable pavers at lay-by on Queen Street East, West of the tracks
+ Completed placement of concrete curbs along the East side of Main Street South, between Queen and North of Station
+ Completed installation of patterned concrete colour splash pads on Queen Street East, from train tracks to Main/Queen Intersection
+ Completed installation of the clock at parkette area at S/E corner of Main/Queen Intersection
+ Completed installation of decorative streetlight poles and pulling underground cables on Main Street, between Main/Queen Intersection and McClellan
+ Continued work on parkette area at S/E corner of Main/Queen Intersection
+ Continued installation of armour stone at Northerly gateway island
+ Commenced placement of concrete sidewalks along the East side of Main Street South, between Queen and North of Station
+ Commenced installation of storm sewer on McClellan, between Main and Agnes
+ Commenced road excavation along the East side of Main Street South, between McClellan and 260m to South
 
In the next two weeks, the Contractor will:
+ Complete installation of storm sewer on McClellan, between Main and Agnes
+ Complete road excavation along the East side of Main Street South, between McClellan and 260m to South
+ Complete placement of base asphalt along the East side of Main Street South, between Queen and North of Station
+ Complete placement of top asphalt on Queen Street East/West/Intersection from train tracks to Main/Queen Intersection (see * above)
+ Complete installation of street furniture and waste bins at amenity areas, throughout
+ Complete installation of permeable pavers at parkette area at S/E corner of Main/Queen Intersection
+ Continue work on gateway islands on Main Street, North of Beechgrove
+ Continue placement of concrete sidewalks along the East and West sides of Main Street South, between Queen and McClellan
+ Commence work on gateway monument at Northerly gateway island
+ Commence installation of storm sewer along the West side of Main Street South, between McClellan and 260m to South
+ Commence installation of streetlights along the West side of Main Street South
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.