Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

7/24/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place. Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
Please note that the Region of Peel installed additional temporary speed cushions and signage on Main Street North, North of Mary Street. The type and the location of the cushions was selected by the Town of Caledon. The cushions and signage will remain on the roadway until October 31, 2019.

0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

7/24/2019

0 Comments

 
The roadway is open. Please note that in the next month, the Region of Peel will be undertaking additional resurfacing work on Queen Street East, between Phase 1 Easterly Limit and Railway Tracks North of Queen/Porterfield Intersection (see Google sketch below). The work to be done will include but not be limited to, the removal of existing asphalt and gravel shoulders and replacing it with new/wider asphalt surface to accommodate cycling, replacement of guide rail systems and placement of new thermoplastic line markings. The work will be carried out as Day Work between the hours of 07:00AM and 7:00PM. We anticipate the work to be a very short duration. Further notice on the actual start date will be provided through future updates.
 
In the last two weeks, the Contractor:
+ Completed planting additional shrubs at the gateway monument
+ Completed sealing permeable pavers at lay-by
+ Completed the removal of storage containers
 
In the next two weeks, the Contractor:
+ Complete placement of new thermoplastic pavement markings – yellow lines
+ General site clean-up
0 Comments

Update on Phase 1 & 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

7/9/2019

0 Comments

 
PHASE 1:
The roadway is open.
 In the last two weeks, the Contractor:
  • Completed line painting within the lay-by
  • Partially completed planting additional shrubs at the gateway monument
  • Commenced placement of new thermoplastic pavement markings
 
  • In the next two weeks, the Contractor:
    • Will complete placement of new thermoplastic pavement markings
    • Will complete additional planting at the gateway monument, inside the planter
    • General site clean-up
 
 PHASE 2:
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place.  Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
  •  In the last two weeks, the Contractor:
    • Completed road excavation at Main/Queen Intersection
    • Completed placement of concrete curbs at Main/Queen Intersection
    • Completed placement of base asphalt at Main/Queen Intersection
    • Completed storm sewer installation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Continued installation of the retaining wall at the cemetery
    • Continued underground electrical works, throughout
    • Continued storm sewer installation along the West side of Main Street South, South of Main/Queen Intersection
    • Commenced road excavation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
 
  • In the next two weeks, the Contractor:
    • Will complete road excavation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will complete placement of concrete curbs along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will complete placement of base asphalt along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will commence installation of sidewalks along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will commence road excavation along the West side of Main Street South, South of Main/Queen Intersection, including King Street
    • Will continue installation of the retaining wall at the cemetery
    • Will continue storm sewer installation along the West side of Main Street South, from Main/King Intersection to McClellan
I will continue to provide updates with major milestones and highlights for both Phases of the project. 
 
Once again, should you have any questions, please contact me at 905-791-7800 ext. 8754 or serguei.kabanov@peelregion.ca.
Serguei Kabanov, CD, CET, rcca
Project Manager
Roads – Design and Construction Public Works
10 Peel Centre Drive
Suite ‘B’, 4th Floor
Brampton, Ontario L6T 4B9
Tel: 905-791-7800 ext. 8754
Cell: 416-902-7425
Serguei.kabanov@peelregion.ca
 
 
0 Comments

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.