The roadway is open.
In the last two weeks, the Contractor:
- Completed line painting within the lay-by
- Partially completed planting additional shrubs at the gateway monument
- Commenced placement of new thermoplastic pavement markings
- In the next two weeks, the Contractor:
- Will complete placement of new thermoplastic pavement markings
- Will complete additional planting at the gateway monument, inside the planter
- General site clean-up
PHASE 2:
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place. Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
- In the last two weeks, the Contractor:
- Completed road excavation at Main/Queen Intersection
- Completed placement of concrete curbs at Main/Queen Intersection
- Completed placement of base asphalt at Main/Queen Intersection
- Completed storm sewer installation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Continued installation of the retaining wall at the cemetery
- Continued underground electrical works, throughout
- Continued storm sewer installation along the West side of Main Street South, South of Main/Queen Intersection
- Commenced road excavation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
- In the next two weeks, the Contractor:
- Will complete road excavation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Will complete placement of concrete curbs along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Will complete placement of base asphalt along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Will commence installation of sidewalks along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Will commence road excavation along the West side of Main Street South, South of Main/Queen Intersection, including King Street
- Will continue installation of the retaining wall at the cemetery
- Will continue storm sewer installation along the West side of Main Street South, from Main/King Intersection to McClellan
Once again, should you have any questions, please contact me at 905-791-7800 ext. 8754 or [email protected].
Serguei Kabanov, CD, CET, rcca
Project Manager
Roads – Design and Construction Public Works
10 Peel Centre Drive
Suite ‘B’, 4th Floor
Brampton, Ontario L6T 4B9
Tel: 905-791-7800 ext. 8754
Cell: 416-902-7425
[email protected]