+ 100% Detailed Design is complete;
+ All necessary permits have been applied for;
+ Tendering of the project is scheduled for mid-January with 30-day closing;
+ Commencement of the works is scheduled for March 2019; and
o Section between Beechgrove and McClellan will commence mid-July, 2019
+ Completion of the works is scheduled for December 2019
In addition to the update, please see attached Detour/Construction plan
https://drive.google.com/open?id=1l8sujm-iaRaWkPn7iEwmgBOWUVybN9oH