We would like to provide you with a quick update on the Phase 1 – Queen Street East construction:
In the last two weeks:
• The Contractor commenced installation of sheet piles at Shaws Creek and continued with the excavation and removal of peat material underneath the existing roadway in the vicinity of the CreeIn the next two weeks:
• The Contractor will continue and complete excavation and removal of peat material underneath the existing roadway in the vicinity of the Creek and commence excavation for the new bridge footings.
Serguei Kabanov, Project Manager, will continue to provide updates with major milestones and highlights of the project.