- In the last two weeks, the Contractor:
- Completed temporary diversion of Tributary to the Shaw’s Creek through temporary by-pass culvert
- Completed concrete retaining wall (toe wall) on the South side of Queen Street, West of the railway tracks
- Commenced excavation, framing and placement of reinforcing steel for pre-cast arch culvert footing, West side
- Continued installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
- Continued building proposed roadway on the East side of the Creek by placing limestone materials
- Continued installation of new storm sewer, throughout
- In the next two weeks, the Contractor will:
- Continue building proposed roadway on the East side of the Creek
- Complete storm sewer installation on the West side of the Creek
- Complete pouring concrete for pre-cast arch culvert footing, West side
- Complete the removal of existing concrete box culvert for Tributary to the Shaw’s Creek
- Complete installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
- Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek
- Commence Tributary to the Shaw’s Creek restoration
An update from Serguei Kabanov of the Region of Peel