Queen Street East construction: May 31, 2018
From Serguei Kabanov, Project Manager
- In the last two weeks, the Contractor:
- Commenced installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
- Commenced and completed installation of Low-Impact-Development (LID) underground storage tanks for the proposed lay-by area
- Continued placement of new granular material for the road base in the East end of the project
- In the next two weeks, the Contractor:
- Will continue installation of ‘H’ piles for the new bridge abutments
- Will commence storm sewer installation
- Will commence preliminary work for the Tributary to the Shaw’s Creek by-pass