- In the last two weeks, the Contractor:
- Completed storm sewer installation on the East side of the Creek
- Completed installation of temporary by-pass culvert for the Tributary to the Shaw’s Creek
- Commenced storm sewer installation on the West side of the Creek
- Commenced installation of concrete retaining wall on the South side of Queen Street, West of the railway tracks
- Commenced cutting/filling for the proposed roadway on the East side of the Creek
- Continue installation of ‘H’ piles for the new bridge abutments on the East side of the Creek
- In the next two weeks, the Contractor will:
- Continue building proposed roadway on the East side of the Creek
- Complete storm sewer installation on the West side of the Creek
- Complete concrete retaining wall on the South side of Queen Street, West of the railway tracks
- Commence installation of ‘H’ piles for the new bridge abutments on the West side of the Creek
- Commence the removal of the existing concrete box culvert at the Tributary to the Shaw’s Creek and form new footings
An update from Serguei Kabanov of the Region of Peel