Update from the Region of Peel on Alton Village Streetscaping Phase 1 from Serguei Kabanov, Project Manager

10/2/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between Queen and McClellan – East side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
  • Please note that all fire trucks at Caledon Fire Station 301 are back at the station
  • Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
  • Please note that construction activities are ongoing around the school frontage.  All entrances are open during morning/afternoon rush hours.
 
In the last two weeks, the Contractor:
+ Completed construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Completed asphalt removal, curb and sidewalk along the East side of Main Street South, between Queen and Station
+ Completed road excavation and granular placement along the East side of Main Street South, between Station and McClellan
+ Completed placement of base and top asphalt at Fire Hall parking lot
+ Continued underground electrical works, throughout
+ Continued driveway reconstruction along the West side of Main Street South, between King and McClellan
+ Commenced installation of lattice fence installation at the gas station
+ Commenced installation of chain link and decorative fences installations on Queen
+ Commenced installation of decorative streetlight poles and luminaires on Queen and Main
+ Commenced installation of storm sewer along the East side of Main Street South, between Queen and Station
+ Commenced construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
 
In the next two weeks, the Contractor will:
+ Complete installation of storm sewer along the East side of Main Street South, between Queen and Edmund
+ Complete construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Complete installation of lattice fence installation at the gas station
+ Complete installation of chain link and decorative fences installations on Queen
+ Complete placement of concrete curbs along the East side of Main Street South, between North of Station and McClellan
+ Continue underground electrical works, throughout
+ Commence placement of sidewalks along the East and West sides of Main Street South, between Station and McClellan
+ Commence forming retaining wall at the cemetery
+ Commence installation of storm sewer along the East side of Main Street South, between Edmund and Station
+ Commence road excavation and granular placement along the East side of Main Street South, between Queen and Edmund
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.