• Please note that all fire trucks at Caledon Fire Station 301 will be brought back to the station on September 25/19
• Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
• Please note that construction activities are ongoing around the school frontage. All entrances are open during morning/afternoon rush hours.
In the last two weeks, the Contractor:
+ Completed road excavation and placement of granular material along the East side of Main Street South, between Beechgrove and South of McClellan
+ Completed road excavation and placement of granular material along the West side of Main Street South, between Beechgrove and South of McClellan
+ Completed installation of gateway islands – curbs, between Beechgrove and South of McClellan
+ Completed placement of base asphalt along the East and West sides of Main Street South, between Beechgrove and South of McClellan
+ Completed lot excavation, granular placement and concrete pad placement at Fire Hall parking lot
+ Completed watermain service relocation to Alton Public School
+ Completed granular placement along the West side of Main Street South, at cemetery
+ Completed installation of curb along the West side of Main Street South, at cemetery
+ Completed placement of base asphalt along the West side of Main Street South, at cemetery
+ Continued underground electrical works, throughout
+ Continued construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Continued driveway reconstruction along the West side of Main Street South, between King and McClellan
In the next two weeks, the Contractor will:
+ Complete construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Complete asphalt removal, curb and sidewalk along the East side of Main Street South, between Queen and Station (traffic will be shifted to the West side of Main, from Queen to Station on Thursday, Sep 19)
+ Complete road excavation and granular placement along the East side of Main Street South, between Station and McClellan
+ Complete chain link and decorative fences installations on Queen
+ Complete lattice fence installation at the gas station
+ Complete placement of base and top asphalt at Fire Hall parking lot
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Commence installation of streetlight poles on Queen Street East
+ Commence storm sewer infiltration chambers along the East side of Main Street South, between Queen and Station