* Please note that we are tentatively scheduling placement of top asphalt and permanent line painting on Queen Street East, from Main/Queen Intersection to train tracks for the upcoming Wednesday, November 20, 2019, weather dependent. The work will commence at the train tracks and progress Westerly. During that work, Queen Street East will be temporary closed with detour and Pay Duty Officers in place. Further update on the closure will be provided on Monday, November 18, 2019.
In the last two weeks, the Contractor:
+ Completed asphalt removal, road excavation and granular placement on McClellan, between Main and Agnes
+ Completed installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Completed installation of lattice fence installation at the gas station
+ Completed installation of chain link fence on Queen Street East, West of the tracks
+ Completed installation of permeable pavers at lay-by on Queen Street East, West of the tracks
+ Completed placement of concrete curbs along the East side of Main Street South, between Queen and North of Station
+ Completed installation of patterned concrete colour splash pads on Queen Street East, from train tracks to Main/Queen Intersection
+ Completed installation of the clock at parkette area at S/E corner of Main/Queen Intersection
+ Completed installation of decorative streetlight poles and pulling underground cables on Main Street, between Main/Queen Intersection and McClellan
+ Continued work on parkette area at S/E corner of Main/Queen Intersection
+ Continued installation of armour stone at Northerly gateway island
+ Commenced placement of concrete sidewalks along the East side of Main Street South, between Queen and North of Station
+ Commenced installation of storm sewer on McClellan, between Main and Agnes
+ Commenced road excavation along the East side of Main Street South, between McClellan and 260m to South
In the next two weeks, the Contractor will:
+ Complete installation of storm sewer on McClellan, between Main and Agnes
+ Complete road excavation along the East side of Main Street South, between McClellan and 260m to South
+ Complete placement of base asphalt along the East side of Main Street South, between Queen and North of Station
+ Complete placement of top asphalt on Queen Street East/West/Intersection from train tracks to Main/Queen Intersection (see * above)
+ Complete installation of street furniture and waste bins at amenity areas, throughout
+ Complete installation of permeable pavers at parkette area at S/E corner of Main/Queen Intersection
+ Continue work on gateway islands on Main Street, North of Beechgrove
+ Continue placement of concrete sidewalks along the East and West sides of Main Street South, between Queen and McClellan
+ Commence work on gateway monument at Northerly gateway island
+ Commence installation of storm sewer along the West side of Main Street South, between McClellan and 260m to South
+ Commence installation of streetlights along the West side of Main Street South