* Please note that we will be commencing reconstruction of McClellan Road, from Main to Agnes on Monday, November 4, 2019. Road excavation and granular placement will commence at Main Street and progress to the West. It is anticipated to complete all excavation and granular placement within 5-6 days. All trucks with new granular (long larger trucks) will be arriving to McClellan from Main Street and backing into. All trucks with excavated material (shorter smaller trucks) will be leaving through McClellan-Agnes-King-Main. In preparation for road excavation on Monday, McClellan road will be milled and placed on gravel this coming Friday, November 1, 2019. All entrances will be ramped and proper signage will be placed. Starting Monday, November 4, 2019, McClellan Road will be closed to through traffic between 08:00AM and 5:00PM. During those hours, access to the West part of Alton Village shall be through King-Agnes. Emergency access will be provided.
In the last two weeks, the Contractor:
+ Completed placement of base asphalt along the East side of Main Street South, between McClellan and North of Station
+ Completed installation of storm sewer and underground infiltration chambers along the East side of Main Street South, between Edmund and North of Station
+ Completed construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed installation of decorative fences installations on Queen Street East, from train tracks to East of Main/Queen Intersection
+ Completed tree planting on Queen Street East, from train tracks to East of Main/Queen Intersection and on Main Street, from Beechgrove to 360m South of McClellan
+ Completed placement of top soil on Queen Street East, from train tracks to East of Main/Queen Intersection and on Main Street, from Beechgrove to McClellan
+ Completed placement of sod at the Fire Hall and on Queen Street East, from train tracks to East of Main/Queen Intersection
+ Completed road excavation and granular placement along the East side of Main Street South, between Queen and North of Station
+ Continued installation of decorative streetlight poles and pulling underground cables, throughout
+ Continued work on parkette area at S/E corner of Main/Queen Intersection
+ Commenced installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Commenced installation of armour stone at Northerly gateway island
+ Commenced construction of amenity/rest area in front of the old school
In the next two weeks, the Contractor:
+ Complete asphalt removal, road excavation and granular placement on McClellan, between Main and Agnes (see ‘*’ above)
+ Complete installation of storm sewer along the East side of Main Street South, between McClellan and 260m to South
+ Complete installation of lattice fence installation at the gas station
+ Complete installation of chain link fence on Queen Street East
+ Complete installation of permeable pavers at lay-by on Queen Street East
+ Complete installation of permeable pavers at parkette area at S/E corner of Main/Queen Intersection
+ Commence installation of storm sewer on McClellan, between Main and Agnes
+ Commence placement of concrete curbs along the East side of Main Street South, between Queen and North of Station
+ Commence road excavation along the East side of Main Street South, between McClellan and 260m to South
+ Commence installation of patterned concrete colour splash pads on Queen Street East, from train tracks to East of Main/Queen Intersection
+ Commence placement of concrete sidewalks, throughout
+ Continue work on gateway islands on Main Street, North of Beechgrove