Alton Village Association
  • Home
  • Community Updates
  • Community Links
  • Alton Village Square
  • Community Gardens / Butterflyway
  • Events
  • Community Life / Visitor Information
  • History
    • Historical Perspective of Alton Village
  • About the A.V.A
  • Alton Neighbourhood Watch
  • Photo Gallery
  • Location
  • Contact Us
  • Non-clickable Page

Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

12/11/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between South of King and North of Station (at cemetery slope) – West side of the roadway remains temporary closed – signals in place, and Main Street South, between McClellan and 360m South – West side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM.
 
In the last two weeks, the Contractor:
  • Completed storm sewer installation along the West side of Main Street South, between McClellan and 260m to South
  • Completed road excavation and placement of granular material along the West side of Main Street South, between McClellan and 260m to South
  • Completed placement of base asphalt on McClellan, between Main and Agnes
  • Completed placement of concrete sidewalks along the West side of Main Street South, between the Cemetery and King Street
  • Completed installation of armour stone at Northerly gateway island
  • Completed installation of guide rail at N/E corner of Main/Queen Intersection
  • Completed pouring gateway monument
  • Continued installation of permeable pavers on Main Street South
  • Continued installation of permanent roadway signs, throughout
  • Commenced placement of concrete curbs along the East and West sides of Main Street South, between McClellan and 260m to South
  • Commenced forming retaining wall at the cemetery
  • Commenced general site clean-up
 
In the next two weeks, the Contractor will:
  • Complete placement of concrete curbs along the East and West sides of Main Street South, between McClellan and 260m to South
  • Complete placement of base asphalt on Main Street South, between McClellan and 260m to South ​(*tentatively scheduled for mid-next week)
  • Complete installation of street furniture and waste bins at amenity areas on Queen Street East
  • Complete brick and stone work at gateway monument
  • Complete placement of temporary pavement markings on Main Street South
  • Continue forming retaining wall at the cemetery
  • Continue general site clean-up
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    April 2023
    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.