In the last two weeks, the Contractor:
- Completed storm sewer installation along the West side of Main Street South, between McClellan and 260m to South
- Completed road excavation and placement of granular material along the West side of Main Street South, between McClellan and 260m to South
- Completed placement of base asphalt on McClellan, between Main and Agnes
- Completed placement of concrete sidewalks along the West side of Main Street South, between the Cemetery and King Street
- Completed installation of armour stone at Northerly gateway island
- Completed installation of guide rail at N/E corner of Main/Queen Intersection
- Completed pouring gateway monument
- Continued installation of permeable pavers on Main Street South
- Continued installation of permanent roadway signs, throughout
- Commenced placement of concrete curbs along the East and West sides of Main Street South, between McClellan and 260m to South
- Commenced forming retaining wall at the cemetery
- Commenced general site clean-up
In the next two weeks, the Contractor will:
- Complete placement of concrete curbs along the East and West sides of Main Street South, between McClellan and 260m to South
- Complete placement of base asphalt on Main Street South, between McClellan and 260m to South (*tentatively scheduled for mid-next week)
- Complete installation of street furniture and waste bins at amenity areas on Queen Street East
- Complete brick and stone work at gateway monument
- Complete placement of temporary pavement markings on Main Street South
- Continue forming retaining wall at the cemetery
- Continue general site clean-up