- In the last two weeks, the Contractor:
- Completed additional resurfacing work on Queen Street East, between Phase 1 Easterly Limit and Railway Tracks North of Queen/Porterfield Intersection.
- In the next two weeks, the Contractor:
- Complete permanent line markings
- Replace guide rails
- Re-grade boulevard gravel shoulders