- Installed eight digital portable variable message signs in the vicinity of Alton Village advising of upcoming construction
- Installed four project sign boards
- Installed 12 business guidance signs throughout the Village
- Secured site trailer and compound facilities (located north of 14 Agnes Street)
- Commenced removals throughout the project limits: trees
In the next two weeks, the Contractor:
April 11, 2019:
- Will commence watermain installation on Main, between Station and Edmund (see sketch):
- Existing Southbound lane will be temporary closed
- Traffic will be diverted to Northbound lane and North-South direction will be controlled by temporary traffic signals
- Will commence road and boulevard removals along Queen Street East, from Phase 1 to Main/Queen Intersection (see sketch):
- Existing Westbound lane will be temporary closed
- Traffic will be diverted to Eastbound lane and East-West direction will be controlled by temporary traffic signals
- Phase 1:
- Station to Edmund – COMPLETED
- Phase 2:
- Beechgrove to McClellan – ONGOING
- McClellan to Station – upcoming
- Edmund to Main/Queen Intersection – upcoming
- McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
In the Event of an Emergency or Gas Shut Off, please contact the following Enbridge staff:
- First call – Field inspector – Phil Sanderson – 416-998-0568
- Second call – Escalation call, Management – Jeff Bruce – 416-819-3517
- Emergency Dispatch – 1-833-872-3477
FOR YOUR INFORMATION:
- Dufferin County will be completing road resurfacing and select culvert replacements on County Road 23, between Dufferin County Road 23 (B-Line) and Peel Regional Road 136 (Porterfield Road)
- During construction of Phase 2, Canada Post relocated existing super boxes (mail boxes) from N/W corners of McClellan/Main and King/Main to Station Street, between Alton School and Library. New mailboxes will be reinstalled to original location once construction is complete