+ The Contractor is anticipated to mobilize on site Wednesday, March 20, 2019 and set up signage, barrels and a field office
+ Pre-Construction meeting will take place on Monday, March 25, 2019
The Contractor is anticipated to commence work on the new storm sewer and water-mains Tuesday, March 26, 2019:
- New storm sewer installation on Queen Street East, between railway tracks and Main Street and on Main Street South, between Queen Street East and McClellan Road
- Relocation of the water-main on Main Street South, between Station Street and Edmund Street
*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
Phase 1:
+ Station Street to Edmund Street – The new main and all service transfers will be completed by Friday, March 22, 2019; the old main along the West side of the Cemetery slope will be decommissioned and abandoned
Phase 2:
+ Station Street to McClellan Road – Work will commence on Monday, March 25, 2019
+ Main/Queen Intersection to Edmund Street – Work will commence in two weeks
+ McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
+ Beechgrove to McClellan – upcoming
March 26, 2019