Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

8/21/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place, Main Street South, between Beechgrove and South of McClellan – East side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
In the last four weeks, the Contractor:
+ Completed installation of sidewalks along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed placement of base asphalt along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed road excavation on King Street
+ Completed placement of concrete curbs on King Street
+ Completed placement of base asphalt along the West side of Main Street South, South of Main/Queen Intersection up to and including King Street
+ Completed storm sewer connections at Fire Hall and Station Street
+ Completed drilling caissons at the Cemetery and removed crane and excavated temporary ‘fill’ material
+ Completed placement of concrete curbs and centre median islands along the West side of Main Street, between Station Street and McClellan
+ Completed placement of base asphalt along the West side of Main Street South, between Station Street and McClellan
+ Completed the removal of asphalt parking lot at Fire Station
+ Continued underground electrical works, throughout
+ Continued road culvert installations on Main Street South, South of McClellan
+ Continued road excavation, throughout

In the next two weeks, the Contractor will:
+ Complete the removal of existing asphalt along the East side of Main Street South, between Station and McClellan and Beechgrove and South of McClellan
+ Complete road excavation along the West side of Main Street South, at cemetery 
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Commence construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Commence excavation along the East side of Main Street South, between Beechgrove and South of McClellan

0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    August 2023
    April 2023
    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.