In the last four weeks, the Contractor:
+ Completed installation of sidewalks along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed placement of base asphalt along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed road excavation on King Street
+ Completed placement of concrete curbs on King Street
+ Completed placement of base asphalt along the West side of Main Street South, South of Main/Queen Intersection up to and including King Street
+ Completed storm sewer connections at Fire Hall and Station Street
+ Completed drilling caissons at the Cemetery and removed crane and excavated temporary ‘fill’ material
+ Completed placement of concrete curbs and centre median islands along the West side of Main Street, between Station Street and McClellan
+ Completed placement of base asphalt along the West side of Main Street South, between Station Street and McClellan
+ Completed the removal of asphalt parking lot at Fire Station
+ Continued underground electrical works, throughout
+ Continued road culvert installations on Main Street South, South of McClellan
+ Continued road excavation, throughout
In the next two weeks, the Contractor will:
+ Complete the removal of existing asphalt along the East side of Main Street South, between Station and McClellan and Beechgrove and South of McClellan
+ Complete road excavation along the West side of Main Street South, at cemetery
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Commence construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Commence excavation along the East side of Main Street South, between Beechgrove and South of McClellan