In the last two weeks, the Contractor:
- Completed storm sewer installation along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Completed installation of new watermain services on the West side of Main Street South, between King and Station
- Continued road excavation and granular placement along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Continued installation of vegetated retaining wall along the North side of Queen Street East, West of the train tracks
- Continued installation of crane platform – fill at cemetery slope, between , between King and Station
In the next two weeks, the Contractor will:
- Complete decommissioning – plugging of existing watermain between Station and King, including the removal of hydrant
- Complete installation of crane platform – fill at cemetery slope, between , between King and Station
- Continue and complete installation of vegetated retaining wall along the North side of Queen Street East, West of the train tracks
- Continue and complete road excavation and granular placement along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Commence and complete relocation of the school flashing beacon at the cemetery further to the north, away from crane pad – fill
- Commence storm sewer installation at Main/Queen Intersection
- Commence road excavation at Main/Queen Intersection (some lanes at the intersection may be left on gravel for a short duration)
- Commence storm sewer installation along the West side of Main Street South, from Main/Queen Intersection to King
- Commence road excavation along the West side of Main Street South, from Main/Queen Intersection to King
- Commence placement of concrete curb along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
- Commence installation of the retaining wall at the cemetery
- Commence underground electrical work along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
Phase 1:
Station to Edmund – COMPLETED
Phase 2:
Edmund to Main/Queen Intersection – COMPLETED
Station to McClellan – COMPLETED
McClellan (Main to Agnes) – COMPLETED
McClellan to Beechgrove – COMPLETED
McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming