+ Improving Main Street South and Queen Street East, including road reconstruction, drainage and boulevard improvements, providing on-street parking, decorative street lighting, streetscaping enhancements and landscaping.
The work includes, but is not limited to:
+ asphalt removal, road excavation and boulevard grading;
+ installation of new:
- storm sewer
- retaining wall structure at the cemetery with architectural finishes
- vegetated retaining wall
- barrier curbs
- decorative coloured pattern concrete splash pads
- wider concrete sidewalks
- decorative architectural streetlighting
- rest areas with street furniture
- gateway features at South end (traffic calming measures); and
- parkette area with town clock
+ improved pavement markings
l+ andscaping
+ minor related works; and,
+ Improvements to Caledon Fire Station 301 parking lot.
Where?
+ Main Street South, from Beechgrove Sideroad to Queen Street East
+ Queen Street East from Main Street South to East of Railway Tracks
When?
+ Start: March, 2019
+ Finish: December 20, 2019, weather permitting
main_street_2019-03-01.pdf |