Please note that all fire trucks at Caledon Fire Station 301 were relocated to an alternate location for 3 weeks during parking lot construction, starting September 4/19
Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
Please note that construction activities are ongoing around the school frontage. All entrances are open during morning/afternoon rush hours.
In the last two weeks, the Contractor:
+ Completed the removal of existing asphalt along the East side of Main Street South, between Beechgrove and South of McClellan
+ Completed road excavation and placement of granular material along the East side of Main Street South, between Beechgrove and South of McClellan
+ Completed the removal of existing asphalt along the West side of Main Street South, between Beechgrove and South of McClellan
+ Completed road excavation along the West side of Main Street South, at cemetery
+ Continued underground electrical works, throughout
+ Commenced granular placement along the West side of Main Street South, at cemetery
+ Commenced road excavation and placement of granular material along the West side of Main Street South, between Beechgrove and South of McClellan
+ Commenced lot excavation and granular placement at Fire Hall parking lot
+ Commenced construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
In the next two weeks, the Contractor will:
+ Complete road excavation and placement of granular material along the East side of Main Street South, between Beechgrove and South of McClellan
+ Complete installation of gateway islands – curbs, between Beechgrove and South of McClellan
+ Complete placement of base asphalt along the East and West sides of Main Street South, between Beechgrove and South of McClellan
+ Complete lot excavation, granular placement and concrete pad placement at Fire Hall parking lot
+ Complete watermain service relocation to Alton Public School
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Continue construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan