Queen Street East construction: Sep 4, 2018
From Serguei Kabanov, Project Manager
In the last two weeks, the Contractor:
- Completed forming, placement of reinforcing steel and pouring concrete for the new bridge abutment, West side
- Completed forming, placement of reinforcing steel and pouring concrete for pre-cast arch culvert wing walls, South side
- Commenced installation of vegetated retaining walls near pre-cast arch culvert
- Continued backfilling pre-cast arch culvert
- Continue installation of vegetated retaining walls and backfilling pre-cast arch culvert
- Continue placement of curbs and sidewalks
- Complete channel restoration and open the Tributary and decommission temporary by-pass pipe
- Complete the removal of sheet piles and backfilling of the new bridge abutment, West side
- Commence forming ballast walls at the new bridge abutments, East and West sides