In the last two weeks, the Contractor:
0 Comments
Update on Phase 1 and 2 Alton Construction Dec 19, 2018 from Serguei Kabanov, Project Manager THE ROAD IS NOW OPEN!! In the last two weeks, the Contractor: + Completed installation of the new Alton Grange sign + Completed installation of guide rail and chain link fence + Completed installation of luminaires, decorative pedestrian streetlight mast arms, banner arms and flower pot holders, throughout + Completed installation of signage + Completed temporary line painting/markings + Continued gateway monument construction; installed lettering In the early 2019, the Contractor will: + Complete installation of bridge and culvert railings + Continue gateway monument construction, pending the weather (will not affect road operation) In the Spring, 2019, the Contractor will come back to complete the following: + Complete gateway monument construction + Complete pattern colour concrete splash pad installation between the curb and the sidewalk, throughout (continuous pour to achieve uniform look) + Complete minor sidewalk installation + Complete colour staining of bridge and culvert parapet walls (continuous staining to achieve uniform look) + Install pier caps on bridge and culvert parapet walls + Complete outstanding driveway asphalt + Complete placement of top asphalt and permanent (durable) thermoplastic line markings + Complete final grading touch-ups, top soil, seeding and sod + Address final requests and deficiencies, if any IMPORTANT INFORMATION FOR THE WINTER PHASE 1: + Contractor will demobilize off site as of Wednesday, December 19, 2018. The Contractor provided emergency numbers and will be available to respond, if needed, over the winter months. Over the winter months, the roadway will be maintained by the Regional Operations Department. + Both site trailers will remain near the Pumping Station until the Spring. At that time, if our current Vendor is successful on winning Phase 2, both trailers will remain until December 2019. If not, they will be removed around May/June and a new Vendor will select a new location within Phase 2. + All newly constructed sidewalks will be kept closed until Spring 2019 due to: a small section of incomplete sidewalk around the bridge area, outstanding bridge and culvert railings and incomplete pattern colour concrete splash pads. Proper signage was placed. The Town of Caledon was notified. Sidewalks will not be plowed. + Newly constructed lay-by will be kept closed until Spring 2019 due to: incomplete permanent (durable) thermoplastic line markings for parking stalls and sidewalks being closed. Proper signage was placed. The Regional Operations Department was notified. Lay-by will not be plowed. + All newly installed ‘share the road’ signs (bicycle signage) will be bagged until Spring 2019 due to: incomplete permanent (durable) thermoplastic line markings. + Install and keep until March two Portable Variable Message Broads advising of the new speed limit and road conditions ahead PHASE 2: + We are hoping to secure a Vendor for Phase 2 works by the end of February, 2019. The project will commence by the end of March + Enbridge Contractor will commence gas main relocations along Main Street South based on the following preliminary schedule: + Edmund Street to Station Street (east side of the road) – January to March + Queen Street to Edmund / Station Street to Beechgrove (east side of the road) – February to June + Most of the work will be done underground using directional drilling method. Sending and receiving shafts will be required at various locations. Some customers will be reconnected to the new main, once completed. Sub-station at N/W corner of McClellan Road will be relocated to S/W corner Serguei, on behalf of the Alton Village Association we wish to thank you for keeping us up-to-date on the progress of your work on Queen St. East. Not only did you keep residents informed, but also involved by listening patiently to concerns and suggestions. The photos you provided helped us understand and appreciate the true scope of the project. We congratulate you and your team for bringing the project in ahead of schedule, a feat which seems to be quite rare these days!
The improvements initiated by Region of Peel on Queen St. East included reconstruction of the bridge and culvert over Shaw’s Creek, drainage and boulevard improvements, on-street parking, decorative street lighting, streetscaping enhancements and landscaping. We appreciated the Public Information Sessions which allowed interested residents to be part of the process, and now we all look forward to seeing those concept drawings become reality. Again, thanks to you and everyone who worked so hard to bringing the project in ahead of time. Sincerely, The Alton Village Association In the last two weeks, the Contractor:
+ Completed installation of decorative railing at toe wall and rest area + Completed pouring concrete for parapet walls and posts for the new bridge + Completed bridge deck waterproofing + Completed placement of base asphalt on the new bridge + Commenced installation of guide rail and chain link fence In the next two weeks, the Contractor: + Complete installation of guide rail and chain link fence + Complete installation of luminaires, decorative pedestrian streetlight mast arms, banner arms and flower pot holders, throughout + Complete installation of signage + Complete temporary line painting/markings + Complete installation of bridge and culvert railings + Continue gateway monument construction + Open the road At this time, we are tentatively scheduling to open the roadway on Wednesday, December 19, 2018. In preparation for Queen Street East opening on December 21, 2018, please note important speed reduction changes that are now in effect and enforceable:
+ Existing 80km/h posted speed limit on Main Street/Queen Street East/Porterfield Road will be reduced to 50km/h from 425m north of Beechgrove to 30m south of Beechgrove; + Existing 50km/h posted speed limit on Main Street/Queen Street East/Porterfield Road will be extended from 515m east of Main Street to 1,030 east of Main Street; and + Existing 80km/h posted speed limit on Main Street/Queen Street East/Porterfield Road will be reduced to 60km/h from 1,030m east of Main Street to 1,530m east of Main Street *** Please note that OPP has been notified and the areas will be enforced *** The Directors of your Alton Village Association want to thank everyone who helped and attended our Annual Lighting of the Tree event Saturday Dec 8th at the Alton Village Square.
We'd also like to send a special thanks to + Santa + Our Alton Fire Department + Andrew Welsh our Town Crier + Paul Morin Hosting our event and inviting the community back to his gallery for the showing of The Grinch that Stole Christmas + Eric Wood for leading the community in singing + Vicki Anderson-Daniell for cooking the hot dogs + Spirit Tree for providing Apple Cider + The Reynolds family for providing hot dogs + D&D Commercial Services – Emanuel Cini for providing hot dog buns + The community for providing cookies + McLean-Sherwood Event Rental for providing us with lighting + All Community Volunteers who helped and a special thanks to Rae Brown for all his help. + Mayor Allan Thompson + Area Councillor Lynn Kiernan + Regional Councillor Ian Sinclair + The Region of Peel for providing recycling and garbage bins and pick-up If we have missed anyone we apologized in advance. Hi Alton Residents, Serguei has sent us an update plans for Phase 2 of the Alton Streetscaping project:
+ 100% Detailed Design is complete; + All necessary permits have been applied for; + Tendering of the project is scheduled for mid-January with 30-day closing; + Commencement of the works is scheduled for March 2019; and o Section between Beechgrove and McClellan will commence mid-July, 2019 + Completion of the works is scheduled for December 2019 In addition to the update, please see attached Detour/Construction plan https://drive.google.com/open?id=1l8sujm-iaRaWkPn7iEwmgBOWUVybN9oH The Town of Caledon is notifying all local residents and affected parties of the Alton Village Drainage Study - Phase 2. The purpose of the study is to identify solutions that will alleviate flooding experienced by the Village of Alton. Construction will not occur during this study. The Phase 2 study area is shown in the Key Map below as well as in the PDF from the Town.
Link to PDF; https://drive.google.com/open?id=1H139djqWkb4s3ZAwVdba9w8qyedy_Ivv The Alton Village Association would like to know if any neighbours would be interested in forming a neighbourhood watch program? The OPP have offered their support and can meet with those interested to provide guidance on organizing the program. Please let us know if you are interested in participating or may like to help with organizing/planning. It’s a great way to get to know your neighbours and build a strong community.
In the last two weeks, the Contractor:
+ Completed placement of permeable paver stones at lay-by parking + Completed construction of rest areas, East end of the project + Completed construction of rest areas, West end of the project + Completed installation of street furniture and garbage bins + Completed pouring concrete for approach slabs for the new bridge + Commenced forming and placement of structural steel for parapet walls and posts for the new bridge + Commenced installation of luminaires, decorative pedestrian streetlight mast arms, banner arms and flower pot holders, throughout In the next two weeks, the Contractor will: + Complete placement of curbs and sidewalks, throughout + Complete pouring concrete for parapet walls and posts for the new bridge + Complete bridge deck waterproofing + Complete placement of base asphalt on the new bridge + Continue installation of luminaires, decorative pedestrian streetlight mast arms, banner arms and flower pot holders, throughout + Commence installation of signage + Commence installation of guide rail and chain link fence + Commence gateway monument construction Please Join the Alton Village Association for the
Annual Alton Village Square Christmas Tree Lighting Hear our Town Crier, Meet Santa, Sing Christmas Carols Enjoy Hot Cider & Cookies and later; Join us at Paul Morin’s Gallery (19741 Main St) for a screening of “How the Grinch Stole Christmas” Hot Dogs are $2.00 each 50/50 Draw - Tickets $2.00 each or 3 for $5.00 Cookie Donations Are Welcomed In the last two weeks, the Contractor:
+ Completed the removal of formwork for the new bridge + Completed backfilling the new bridge + Completed forming, reinforcement and pouring concrete sidewalks on the new bridge + Completed placement of top soil and planting new trees + Commenced forming and reinforcement for approach slabs on the new bridge + Continued construction of rest areas: armour stone and permeable pavers, East end of the project + Continued installation of decorative streetlight poles and underground, throughout + Continued placement of armour stone, top soil and new planting at gateway monument In the next two weeks, the Contractor will: + Complete placement of permeable paver stones at lay-by parking + Complete construction of rest areas, East end of the project + Complete construction of rest areas, West end of the project + Complete installation of street furniture and garbage bins + Complete pouring concrete for approach slabs for the new bridge + Complete terraseeding and hydroseeding + Continue placement of curbs and sidewalks, throughout + Continue installation of decorative streetlight poles and underground wire, throughout + Commence placement of pattern colour concrete splash pads, throughout + Commence forming and placement of structural steel for parapet walls and posts for the new bridge Update on Phase 1
Queen Street East construction Oct 17, 2018 from Serguei Kabanov, Project Manager In the last two weeks, the Contractor: + Completed framing underside of the new bridge + Completed installation of remaining vegetated retaining walls + Completed installation of remaining storm sewer + Completed terraseeding slopes and ditches at the East Limit and hydroseeding vegetated retaining wall + Commenced placement of structural steel for the new bridge beck + Commenced forming parapet walls and posts for the new culvert + Continued installation of decorative streetlight poles and underground, throughout + Continued placement of curbs and sidewalks, throughout + Continued road excavation and granular placement at the West Limit In the next two weeks, the Contractor will: + Complete hydroseeding remaining vegetated retaining wall + Complete forming and pouring concrete for parapet walls and posts for the new culvert + Complete placement of structural steel for the new bridge beck + Continue granular placement at the West Limit + Continue placement of curbs and sidewalks, throughout + Continue installation of decorative streetlight poles and underground wire, throughout + Commence placement of base asphalt for the roadway + Commence placement of permeable paver stones at lay-by parking + Commence construction of rest areas, throughout Station 301 Alton Fire Hall - Open House Pancake Breakfast served by your Firefighters. Enjoy a pancake breakfast & meet your local firefighters.
Update
Due to contractor material procurement delays, the road closure for Shaws Creek Road Culvert Replacement Project will be extended to: Friday, October 26, 2018 Staff are committed to finishing the project as quickly as possible and appreciate the cooperation of local residents. Hi everyone the Alton Village Association want to remind you that the 2018 Municipal Election is quickly approaching. We encouraging everyone to vote. Remember your vote counts.
DATE/TIME/LOCATION(S) ADVANCED VOTING Saturday, Oct. 6th, 10:00 a.m. to 3:00 p.m. Saturday, Oct. 13th, 10:00 a.m. to 3:00 p.m. Thursday Oct.18th, 12:00 p.m. to 8:00 p.m. Friday Oct. 19th, 12:00 p.m. to 8:00 p.m. Caledon Central Public School 18357 Kennedy Rd. ELECTION DAY MONDAY, Oct. 22, 10:00 a.m. to 8:00 p.m. Alton Public Library 35 Station Street Caledon Central Public School 18357 Kennedy Rd. Inglewood Community Centre 15825 McLaughlin Road Update on the Phase 1
Queen Street East construction: Sep 28, 2018 From Serguei Kabanov, Project Manager In the last two weeks, the Contractor: + Completed forming, placing structural steel and pouring concrete for the new gateway monument footing + Completed installation of precast concrete girders for new bridge + Commenced placement of top soil at the East Limit + Commenced installation of decorative streetlight poles and underground wire at the East Limit of the project and mid-block + Continued installation of vegetated retaining walls + Continued placement of curbs and sidewalks + Continued road excavation and granular placement at the mid-block of the project In the next two weeks, the Contractor will: + Continue installation of vegetated retaining walls + Continue placement of curbs and sidewalks + Continue forming and pouring gateway monument + Continue installation of decorative streetlight poles and underground wire mid-block +Commence forming, placing structural steel and pouring concrete for the new bridge, various components + Commence road excavation and granular placement at the West Limit of the project Update on the Phase 1
Queen Street East construction: Sep 18, 2018 From Serguei Kabanov, Project Manager In the last two weeks, the Contractor: + Completed channel restoration and opened the Tributary to Shaw’s Creek and decommissioned temporary by-pass pipe + Completed the removal of sheet piles and backfilling of the new bridge abutment, West side + Commenced placement of sidewalks at the East Limit + Commenced excavation and forming foundation for the gateway monument + Continued installation of vegetated retaining walls + Continued placement of curbs for the new centre median islands + Continued road excavation and granular placement at the East Limit of the project In the next two weeks, the Contractor will: + Continue installation of vegetated retaining walls + Continue road excavation and granular placement between the new culvert and bridge + Continue placement of curbs and sidewalks + Continue forming and pouring gateway monument + Commence and complete the delivery and installation of precast concrete girders for the new bridge + Commence forming, placing structural steel and pouring concrete for the new bridge, various components + Commence installation of decorative streetlight poles and underground wire at the East Limit of the project Highpoint Side Road will be closed between Porterfield Road and Willoughby Road for local
railway maintenance. Local access will be maintained however, due to the nature of the project, Highpoint Side Road will be closed to through traffic. Anticipated construction dates: Monday, September 24, 2018 (anticipated road closure date) Sunday, September 30, 2018 (anticipated completion date) There will be no through traffic on Highpoint Side road during the road closure. All questions regarding this project can be directed to Service Caledon at: 905 584 2272 x.7750 SCHEDULED WATER SUPPLY INTERRUPTION
Dear Customer: The Region of Peel Public Works department regularly maintains and repairs the water system to make sure you have a reliable supply of quality drinking water. Sometimes we must turn off your water supply while we do the work. In the next few days, we will be working in your area and will have to turn off your water for a few hours. Your water will be turned off on Monday, September 17, 2018 from approximately 12:00 p.m. to 4:00 p.m. However, if the weather is bad or if a problem arises, we will reschedule the work and will let you know the new date and time. When we turn the water back on, air in the pipes may make the water cloudy and your plumbing may vibrate or make noise. If this happens, you can remove the air by briefly turning on your taps from the lowest to the highest faucet in the building (that is, starting in the basement/first floor and finishing on the top floor). Flush the toilets as well. You should only have to run the water for 10 to 30 seconds, but keep running it until the water is clear, and any vibration or noise has stopped. If your water meter starts to leak, call Water Meter Installations Dispatch at: (905) 791-7800 Ext. 3226 (8:30 a.m. to 4:30 p.m. - Monday to Friday) (905) 791-7800 Ext. 4409 (After hours or Statutory Holidays) Date and Time: Monday, September 17, 2018 from 12:00 p.m. to 4:00 p.m. Location: 2938 Charleston Sideroad, Caledon Addresses Affected: #’s 2940, 2939 and 2943 Charleston Sideroad #2 McFaul Street #155 Troiless Street #28 Elizabeth Street Shaun Hussain Foreman, Construction Inspection Engineering Technical Services Operations Support Public Works Department Update on the Phase 1
Queen Street East construction: Sep 4, 2018 From Serguei Kabanov, Project Manager In the last two weeks, the Contractor:
Please note the Town are advising of upcoming road construction that will cause a road closure. Location: Shaws Creek Road, between Highpoint Side Road and Caledon East Garafraxa Townline From September 4th Through October 1st. Download the PDF file for details and the detour route.
An update from Serguei Kabanov, Project Manager at the Region of Peel
I would like to provide you with a quick update on the Phase 1 – Queen Street East construction: In the last two weeks, the Contractor: o Completed installation of ‘H’ piles for the new bridge abutments, East side o Completed pouring concrete for pre-cast arch culvert footing, West side o Commenced excavation, forming, placement of reinforcing steel and pouring concrete for pre-cast arch culvert footing, East side o Completed existing bridge removal o Completed installation of pre-cast arch culvert and commenced backfilling o Commenced excavation, forming, placement of reinforcing steel new bridge footing, East side o Commenced pouring new concrete curbs on the East side of the Creek o Commenced Tributary to Shaw’s Creek restoration In the next two weeks, the Contractor will: o Continue backfilling pre-cast arch culvert o Continue Tributary to Shaw’s Creek restoration o Complete the removal of existing bridge footings, both sides o Complete pouring concrete for the new bridge abutment, East side o Commence excavation for the new bridge abutment, West side o Commence installation of ‘H’ piles for the new bridge abutments, West side o Commence underground electrical works An update from Serguei Kabanov, Project Manager at the Region of Peel
This afternoon, the Contractor successfully installed pre-cast arch culvert over the Tributary to Shaw’s creek. |