Update from the Region of Peel on Alton Village Streetscaping Phase 1 from Serguei Kabanov, Project Manager

10/2/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between Queen and McClellan – East side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
  • Please note that all fire trucks at Caledon Fire Station 301 are back at the station
  • Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
  • Please note that construction activities are ongoing around the school frontage.  All entrances are open during morning/afternoon rush hours.
 
In the last two weeks, the Contractor:
+ Completed construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Completed asphalt removal, curb and sidewalk along the East side of Main Street South, between Queen and Station
+ Completed road excavation and granular placement along the East side of Main Street South, between Station and McClellan
+ Completed placement of base and top asphalt at Fire Hall parking lot
+ Continued underground electrical works, throughout
+ Continued driveway reconstruction along the West side of Main Street South, between King and McClellan
+ Commenced installation of lattice fence installation at the gas station
+ Commenced installation of chain link and decorative fences installations on Queen
+ Commenced installation of decorative streetlight poles and luminaires on Queen and Main
+ Commenced installation of storm sewer along the East side of Main Street South, between Queen and Station
+ Commenced construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
 
In the next two weeks, the Contractor will:
+ Complete installation of storm sewer along the East side of Main Street South, between Queen and Edmund
+ Complete construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Complete installation of lattice fence installation at the gas station
+ Complete installation of chain link and decorative fences installations on Queen
+ Complete placement of concrete curbs along the East side of Main Street South, between North of Station and McClellan
+ Continue underground electrical works, throughout
+ Commence placement of sidewalks along the East and West sides of Main Street South, between Station and McClellan
+ Commence forming retaining wall at the cemetery
+ Commence installation of storm sewer along the East side of Main Street South, between Edmund and Station
+ Commence road excavation and granular placement along the East side of Main Street South, between Queen and Edmund
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 1 from Serguei Kabanov, Project Manager

10/2/2019

0 Comments

 
In the last two weeks, the Contractor:
+ Completed re-grading of boulevard gravel shoulders
+ Completed replacement of guide rails
 
In the next two weeks, the Contractor will:
+ Complete replacement and planting of new shrubs/trees

Picture
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 1 from Serguei Kabanov, Project Manager

9/18/2019

0 Comments

 
In the last two weeks, the Contractor:
+ Completed placement of permanent line markings
+ Commenced re-grading boulevard gravel shoulders

In the next two weeks, the Contractor will:
+ Complete re-grading of boulevard gravel shoulders
+ Complete replacement of guide rails
+ Complete replacement and planting of new shrubs/trees

Picture
Picture
0 Comments

Update from the Region of Peel on Alton Village Streetscaping Phase 2 from Serguei Kabanov, Project Manager

9/18/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between King and Station – West side of the roadway remains temporary closed – signals in place, Main Street South, between Station and McClellan – East side of the roadway remains temporary closed – signals in place, Main Street South. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
• Please note that all fire trucks at Caledon Fire Station 301 will be brought back to the station on September 25/19
• Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
• Please note that construction activities are ongoing around the school frontage. All entrances are open during morning/afternoon rush hours.

In the last two weeks, the Contractor:
+ Completed road excavation and placement of granular material along the East side of Main Street South, between Beechgrove and South of McClellan
+ Completed road excavation and placement of granular material along the West side of Main Street South, between Beechgrove and South of McClellan
+ Completed installation of gateway islands – curbs, between Beechgrove and South of McClellan
+ Completed placement of base asphalt along the East and West sides of Main Street South, between Beechgrove and South of McClellan
+ Completed lot excavation, granular placement and concrete pad placement at Fire Hall parking lot
+ Completed watermain service relocation to Alton Public School
+ Completed granular placement along the West side of Main Street South, at cemetery
+ Completed installation of curb along the West side of Main Street South, at cemetery
+ Completed placement of base asphalt along the West side of Main Street South, at cemetery
+ Continued underground electrical works, throughout
+ Continued construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Continued driveway reconstruction along the West side of Main Street South, between King and McClellan

In the next two weeks, the Contractor will:
+ Complete construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Complete asphalt removal, curb and sidewalk along the East side of Main Street South, between Queen and Station (traffic will be shifted to the West side of Main, from Queen to Station on Thursday, Sep 19)
+ Complete road excavation and granular placement along the East side of Main Street South, between Station and McClellan
+ Complete chain link and decorative fences installations on Queen
+ Complete lattice fence installation at the gas station
+ Complete placement of base and top asphalt at Fire Hall parking lot
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas and armour stone retaining walls along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Commence installation of streetlight poles on Queen Street East
+ Commence storm sewer infiltration chambers along the East side of Main Street South, between Queen and Station
0 Comments

Important Construction Update from the Region of Peel

9/11/2019

0 Comments

 
On Thursday, September 12, 2019, our Contractor will be placing base asphalt on Main Street South, between Beechgrove SD Rd and Alton Greenhouses.  All operations will commence at 6PM and continue overnight into Friday day.  The roadway will be open with one lane of traffic being maintained.  Additional paving will be completed on Friday, on Main Street South, near the Cemetery wall.  All paving will be completed prior to Tour de Headwaters bike race on Saturday.
Picture
0 Comments

Update on Phase 2 Alton Village Streetscaping

9/4/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between King and Station – West side of the roadway remains temporary closed – signals in place, Main Street South, between Station and McClellan – East side of the roadway remains temporary closed – signals in place, Main Street South, between Beechgrove and South of McClellan – West side of the roadway remains temporary closed – signals in place; East side is currently on gravel. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
Please note that all fire trucks at Caledon Fire Station 301 were relocated to an alternate location for 3 weeks during parking lot construction, starting September 4/19
Please note that temporary school crosswalk was relocated to Station and Main Intersection; crossing guard on duty
Please note that construction activities are ongoing around the school frontage. All entrances are open during morning/afternoon rush hours.

 
 In the last two weeks, the Contractor:
+ Completed the removal of existing asphalt along the East side of Main Street South, between Beechgrove and South of McClellan
+ Completed road excavation and placement of granular material along the East side of Main Street South, between Beechgrove and South of McClellan
+ Completed the removal of existing asphalt along the West side of Main Street South, between Beechgrove and South of McClellan
+ Completed road excavation along the West side of Main Street South, at cemetery
+ Continued underground electrical works, throughout
+ Commenced granular placement along the West side of Main Street South, at cemetery
+ Commenced road excavation and placement of granular material along the West side of Main Street South, between Beechgrove and South of McClellan
+ Commenced lot excavation and granular placement at Fire Hall parking lot
+ Commenced construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
 
In the next two weeks, the Contractor will:
+ Complete road excavation and placement of granular material along the East side of Main Street South, between Beechgrove and South of McClellan
+ Complete installation of gateway islands – curbs, between Beechgrove and South of McClellan
+ Complete placement of base asphalt along the East and West sides of Main Street South, between Beechgrove and South of McClellan
+ Complete lot excavation, granular placement and concrete pad placement at Fire Hall parking lot
+ Complete watermain service relocation to Alton Public School
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Continue construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
0 Comments

Update on Phase 1 Alton Village Streetscaping

9/4/2019

0 Comments

 
  •  In the last two weeks, the Contractor:
    • Completed additional resurfacing work on Queen Street East, between Phase 1 Easterly Limit and Railway Tracks North of Queen/Porterfield Intersection.
 
  • In the next two weeks, the Contractor:
    • Complete permanent line markings
    • Replace guide rails
    • Re-grade boulevard gravel shoulders
Picture
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

8/21/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place, Main Street South, between Beechgrove and South of McClellan – East side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
In the last four weeks, the Contractor:
+ Completed installation of sidewalks along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed placement of base asphalt along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
+ Completed road excavation on King Street
+ Completed placement of concrete curbs on King Street
+ Completed placement of base asphalt along the West side of Main Street South, South of Main/Queen Intersection up to and including King Street
+ Completed storm sewer connections at Fire Hall and Station Street
+ Completed drilling caissons at the Cemetery and removed crane and excavated temporary ‘fill’ material
+ Completed placement of concrete curbs and centre median islands along the West side of Main Street, between Station Street and McClellan
+ Completed placement of base asphalt along the West side of Main Street South, between Station Street and McClellan
+ Completed the removal of asphalt parking lot at Fire Station
+ Continued underground electrical works, throughout
+ Continued road culvert installations on Main Street South, South of McClellan
+ Continued road excavation, throughout

In the next two weeks, the Contractor will:
+ Complete the removal of existing asphalt along the East side of Main Street South, between Station and McClellan and Beechgrove and South of McClellan
+ Complete road excavation along the West side of Main Street South, at cemetery 
+ Continue underground electrical works, throughout
+ Commence construction of amenity/rest areas along Queen Street East, from Phase 1 to Main/Queen Intersection
+ Commence forming retaining wall at the cemetery
+ Commence construction of storm sewer infiltration chambers along the East side of Main Street South, between Station and McClellan
+ Commence excavation along the East side of Main Street South, between Beechgrove and South of McClellan

0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

8/21/2019

0 Comments

 
Please note that Graham Bros. Construction Ltd. commenced additional resurfacing work on Queen Street East, between Phase 1 Easterly Limit and Railway Tracks North of Queen/Porterfield Intersection (see Google sketch attached). Please find below work schedule:
+ August 19: roadway open-single lane during the day with flagging, milling/asphalt removal up to Porterfield RD – COMPLETED 
+ August 20: roadway open-single lane during the day with flagging, milling/asphalt removal up to railway tracks – COMPLETED 
+ August 21: roadway open-single lane during the day with flagging, placement of base asphalt up to Porterfield RD – IN PROGRESS
+ August 22: roadway open-single lane during the day with flagging, placement of base asphalt up to railway tracks
+ August 23: roadway closed-OPP pay duty in place during the day, placement of top asphalt
+ August 26: roadway open; shoulders, replacement of guide rail and line painting

All works is scheduled between 07:00am and 7:00pm. Emergency vehicles will be notified and have access. Schedule is weather dependent
Picture
0 Comments

Alton Village Pump Track Opening

8/7/2019

0 Comments

 
The Alton Village Association along with Lynx and Hare Cycles and the Town of Caledon are pleased to announce that our official opening of the bicycle "pump track" in Alton was a great success on Saturday.

Lots of local families came out to show us their biking skills and meet: Caledon Mayor Allan Thompson, former Regional Councillor Barb Shaughnessy and our current Regional Councillor Ian Sinclair. All were really impressed with Mayor Thompson taking the first demonstration lap and logging an impressive first time run of 1:02.

Track designer; Chris Dewar from Transitions Bike Parks came to join in the fun and handed out t-shirts to some of our best riders. In all, 20 participants enjoyed testing out the track and recording lap times for bragging rights and good fun. Our top 3 competitors are :
1. with a time of 23.63 seconds by Colin from Erin
2. with a time of 32.15 seconds by Silas from Alton
3. with a time of 33.30 seconds by Ivan from Alton

A complete list of results and times can be found at
​
Lynx and Hare Cycles

Picture
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

7/24/2019

0 Comments

 
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place. Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
Please note that the Region of Peel installed additional temporary speed cushions and signage on Main Street North, North of Mary Street. The type and the location of the cushions was selected by the Town of Caledon. The cushions and signage will remain on the roadway until October 31, 2019.

0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

7/24/2019

0 Comments

 
The roadway is open. Please note that in the next month, the Region of Peel will be undertaking additional resurfacing work on Queen Street East, between Phase 1 Easterly Limit and Railway Tracks North of Queen/Porterfield Intersection (see Google sketch below). The work to be done will include but not be limited to, the removal of existing asphalt and gravel shoulders and replacing it with new/wider asphalt surface to accommodate cycling, replacement of guide rail systems and placement of new thermoplastic line markings. The work will be carried out as Day Work between the hours of 07:00AM and 7:00PM. We anticipate the work to be a very short duration. Further notice on the actual start date will be provided through future updates.
 
In the last two weeks, the Contractor:
+ Completed planting additional shrubs at the gateway monument
+ Completed sealing permeable pavers at lay-by
+ Completed the removal of storage containers
 
In the next two weeks, the Contractor:
+ Complete placement of new thermoplastic pavement markings – yellow lines
+ General site clean-up
0 Comments

Update on Phase 1 & 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

7/9/2019

0 Comments

 
PHASE 1:
The roadway is open.
 In the last two weeks, the Contractor:
  • Completed line painting within the lay-by
  • Partially completed planting additional shrubs at the gateway monument
  • Commenced placement of new thermoplastic pavement markings
 
  • In the next two weeks, the Contractor:
    • Will complete placement of new thermoplastic pavement markings
    • Will complete additional planting at the gateway monument, inside the planter
    • General site clean-up
 
 PHASE 2:
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place.  Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place.  Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
  •  In the last two weeks, the Contractor:
    • Completed road excavation at Main/Queen Intersection
    • Completed placement of concrete curbs at Main/Queen Intersection
    • Completed placement of base asphalt at Main/Queen Intersection
    • Completed storm sewer installation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Continued installation of the retaining wall at the cemetery
    • Continued underground electrical works, throughout
    • Continued storm sewer installation along the West side of Main Street South, South of Main/Queen Intersection
    • Commenced road excavation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
 
  • In the next two weeks, the Contractor:
    • Will complete road excavation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will complete placement of concrete curbs along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will complete placement of base asphalt along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will commence installation of sidewalks along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
    • Will commence road excavation along the West side of Main Street South, South of Main/Queen Intersection, including King Street
    • Will continue installation of the retaining wall at the cemetery
    • Will continue storm sewer installation along the West side of Main Street South, from Main/King Intersection to McClellan
I will continue to provide updates with major milestones and highlights for both Phases of the project. 
 
Once again, should you have any questions, please contact me at 905-791-7800 ext. 8754 or serguei.kabanov@peelregion.ca.
Serguei Kabanov, CD, CET, rcca
Project Manager
Roads – Design and Construction Public Works
10 Peel Centre Drive
Suite ‘B’, 4th Floor
Brampton, Ontario L6T 4B9
Tel: 905-791-7800 ext. 8754
Cell: 416-902-7425
Serguei.kabanov@peelregion.ca
 
 
0 Comments

Update on Phase 1 &2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

6/26/2019

0 Comments

 
The roadway is open.

In the last two weeks, the Contractor:
  • Completed final driveway restoration and roadway base asphalt repairs, throughout
  • Completed installation of decorative patterned colour concrete splash pads (area between the back of curb and front of sidewalk), throughout
  • Completed power washing and sealing decorative patterned colour concrete splash pads, throughout
  • Completed installation of black ‘ALTON’ letters at the gateway monument
  • Completed placement of top asphalt
  • Commenced placement of new thermoplastic pavement markings
  • In the next two weeks, the Contractor:
  • Will complete placement of new thermoplastic pavement markings
  • Will commence additional planting at the gateway monument
  • General site clean-up

PHASE 2:
The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – South side of the roadway is now temporary closed – signals in place. Main Street South, between King and McClellan – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.

*** What is Happening at the Cemetery side slope, along Main Street?
We continue to construct brand new reinforced concrete retaining wall along the West side of Main Street, fronting Alton Cemetery. The wall is constructed in the flowing stages:
  • Utility relocations: Enbridge and watermain – COMPLETED
  • Temporary closure of Southbound lane and installation of temporary concrete barriers – COMPLETED
  • Placement of temporary ‘fill’ material or cut-off-level (limestone granular material) in order to create safe and stable working platform for the crane – COMPLETED
  • Tree branches clearance/support: the branches for the main tree at the cemetery were tied back – COMPLETED
  • Equipment and material: mobilize crane and drilling equipment – COMPLETED
  • Drilling/Concrete – CONTINUED
  • * 1m in Diameter holes will be drilled side-by-side along the top portion of the slope at various depths
  • Holes will be reinforced with steel I-beams and filled with concrete – caissons
  • Removal of temporary ‘fill’ material or cut-off-level – UPCOMING
  • Excavation of earth slope in front of caissons – UPCOMING
  • Installation of decorative reinforced face to mimic historic church on the East side – UPCOMING

In the last two weeks, the Contractor:
  • Completed installation of low impact development on-street parking on the North side of Queen Street East, West of the tracks
  • Completed storm sewer installation at Main/Queen Intersection (moving southerly)
  • Completed placement of concrete curb along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed installation of sidewalk along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed placement of base asphalt along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection – traffic is switched onto the new road
  • Completed the removal of existing asphalt, curbs and sidewalk along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed the removal of existing asphalt at Main/Queen Intersection
  • Continued installation of the retaining wall at the cemetery
  • Continued underground electrical works, throughout
  • Continued storm sewer installation South of Main/Queen Intersection

In the next two weeks, the Contractor will:
  • Complete road excavation at Main/Queen Intersection
  • Complete placement of concrete curbs and sidewalks at Main/Queen Intersection
  • Complete placement of base asphalt at Main/Queen Intersection
  • Continue installation of the retaining wall at the cemetery
  • Continue storm sewer installation along the West side of Main Street South, from Main/Queen Intersection to McClellan
  • Continue road excavation along the West side of Main Street South, from Main/Queen Intersection to McClellan
  • Commence storm sewer installation along the South side of Queen Street East, from Phase 1 to Main/Queen Intersection

*** Please note Enbridge Gas Distribution (NPL Canada) completed all gas relocations in the Village ***

Picture
Picture
Picture
Picture
Picture
Picture
Picture
Picture
0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

6/20/2019

0 Comments

 
Queen Street East will be closed to through traffic from Main/Queen Intersection to Queen/Porterfield Intersection.  Monday, June 24, between 07:00AM and 5:00PM, weather permitting.

PHASE 1:
As per the previous UPDATE #40, our Contractor will be completing placement of top asphalt and new thermoplastic pavement markings on Monday, June 24, between 07:00AM and 5:00PM, weather permitting.

As such, Queen Street East will be closed to through traffic from Main/Queen Intersection to Queen/Porterfield Intersection.

We will be notifying all emergency services. Local traffic, West of the railway tracks, can entire/exit from the West only. Local traffic, East of railway tracks, will have limited access to properties due to paving operations and encouraged to vacate driveways (if needed) prior to 07:00 AM. OPP Pay Duty Police Officers will be on site to assist with traffic control and roadway closures.

We will be bringing in additional equipment and manpower to complete this work as quickly as possible. We greatly appreciate your cooperation in this matter.

I will continue to provide updates with major milestones and highlights for both Phases of the project.

Once again, should you have any questions, please contact me at

905-791-7800 ext. 8754 or serguei.kabanov@peelregion.ca.

Serguei Kabanov, CD, CET, rcca
Project Manager Roads – Design and Construction Public Works
10 Peel Centre Drive Suite ‘B’, 4th Floor
Brampton, Ontario
L6T 4B9
Tel: 905-791-7800 ext. 8754
Cell: 416-902-7425
Serguei.kabanov@peelregion.ca


Picture
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

5/29/2019

0 Comments

 
 The roadway remains open, with temporary lane closures: Queen Street East, between railway tracks and Main/Queen Intersection – North side of the roadway remains temporary closed – signals in place. Main Street South, between King and Station – West side of the roadway remains temporary closed – signals in place. Contractor will be working most Saturdays, 07:00AM – 4:00PM to expedite work.
 
 In the last two weeks, the Contractor:
  • Completed storm sewer installation along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Completed installation of new watermain services on the West side of Main Street South, between King and Station
  • Continued road excavation and granular placement along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Continued installation of vegetated retaining wall along the North side of Queen Street East, West of the train tracks
  • Continued installation of crane platform – fill at cemetery slope, between , between King and Station
  
In the next two weeks, the Contractor will:
  • Complete decommissioning – plugging of existing watermain between Station and King, including the removal of hydrant
  • Complete installation of crane platform – fill at cemetery slope, between , between King and Station
  • Continue and complete installation of vegetated retaining wall along the North side of Queen Street East, West of the train tracks
  • Continue and complete road excavation and granular placement along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Commence and complete relocation of the school flashing beacon at the cemetery further to the north, away from crane pad – fill
  • Commence storm sewer installation at Main/Queen Intersection
  • Commence road excavation at Main/Queen Intersection (some lanes at the intersection may be left on gravel for a short duration)
  • Commence storm sewer installation along the West side of Main Street South, from Main/Queen Intersection to King
  • Commence road excavation along the West side of Main Street South, from Main/Queen Intersection to King
  • Commence placement of concrete curb along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  • Commence installation of the retaining wall at the cemetery
  • Commence underground electrical work along the North side of Queen Street East, from Phase 1 to Main/Queen Intersection
  •  
 
*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
 
 
Phase 1:
Station to Edmund – COMPLETED
 
 
Phase 2:
Edmund to Main/Queen Intersection – COMPLETED
Station to McClellan – COMPLETED
McClellan (Main to Agnes) – COMPLETED
McClellan to Beechgrove – COMPLETED
McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming

Picture
Picture
Picture
0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

5/29/2019

0 Comments

 
The roadway remains open, with temporary lane closures between 07:00AM and 5:00PM, Monday to Friday.
  • In the last two weeks, the Contractor:
    • Completed placement of top soil/seed – terraseeding, throughout
    • Completed general parging and sealing a the bridge and culvert structures
    • Completed general site clean-up
 
  • In the next two weeks, the Contractor:
    • Will commence and complete final driveway restoration and roadway base asphalt repairs, throughout (repairs to the asphalt at the railway tracks is scheduled for May 30-31)
    • Will commence and complete installation of decorative patterned colour concrete splash pads (area between the back of curb and front of sidewalk), throughout
    • Will commence and complete additional planting at the gateway monument
    • Will commence and complete installation of black ‘ALTON’ letters at the gateway monument
Picture
0 Comments

Annual General Meeting

5/9/2019

0 Comments

 
Picture
Location: Paul Morin Gallery – 19741 Main Street Alton
Date: Tuesday, June 6, 2019
Time: 7:00 p.m.

Agenda

 + Short Business Meeting  
+ Alton Trivia – fun questions on the History of Alton
​
by Jane Ansara
+ Neighbourhood Watch, and Protecting your Property
by Jane Ansara and the Caledon O.P.P.

Please join or renew your annual Alton Village Association 2019 membership. For only $10.00 a year, you can belong to the AVA
See event calendar
0 Comments

Town of Caledon Update

4/30/2019

0 Comments

 
File
https://drive.google.com/open?id=15MVOCMUfx75pMnpJrz4U-yJ8iMTQNkB8
0 Comments

Update on Phase 1 Alton Village Streetscaping from Serguei Kabanov, Project Manager

4/23/2019

0 Comments

 
Our Contractor will be mobilizing back to site this week – April 22, 2019 to complete outstanding works:
+ Storm sewer frame and cover adjustments and minor concrete curb repairs/in-fills 
+ Sidewalk completion around the bridge structure, both sides
+ Installation of decorative patterned colour concrete splash pads (area between the back of curb and front of sidewalk), throughout
+ Masonry work on the gateway monument (see sketch)
+ Installation of decorative bridge pier caps at both structures
+ Decorative staining of both structures
+ Driveways paving
+ Final landscaping touch-ups: sod/seed and shrubs; and
+ Placement of top asphalt and permanent durable thermoplastic line markings
The intention is to complete the project by mid-June or sooner, weather permitting


Picture
In the next two weeks, the Contractor will:
+ Remove both site trailers in front of Alton Pumping Station
Commence concrete works (curbs, sidewalks and splash pads)
+ Commence gateway monument works

Please note that temporary lane closures are expected between 07:00AM and 5:00PM, Monday to Friday in order to complete outstanding boulevard works
Please note that the Region of Peel retained a facilities contractor to complete improvements to Alton Pumping Station. In the next few weeks, you will see additional construction activities in and around the Station. Most of the work will occur inside the Station. Should you have any questions pertaining to that project, please contact Jennifer Lanthier, Project Manager, Water Facilities Engineering & Reliability at Jennifer.Lanthier@peelregion.ca.
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

4/1/2019

0 Comments

 
In the last two weeks, the Contractor:
  • Installed eight digital portable variable message signs in the vicinity of Alton Village advising of upcoming construction
  • Installed four project sign boards
  • Installed 12 business guidance signs throughout the Village
  • Secured site trailer and compound facilities (located north of 14 Agnes Street)
  • Commenced removals throughout the project limits: trees

In the next two weeks, the Contractor:
April 11, 2019:
  • Will commence watermain installation on Main, between Station and Edmund (see sketch):
    • Existing Southbound lane will be temporary closed
    • Traffic will be diverted to Northbound lane and North-South direction will be controlled by temporary traffic signals
Picture
April 11, 2019:
  • Will commence road and boulevard removals along Queen Street East, from Phase 1 to Main/Queen Intersection (see sketch):
    • Existing Westbound lane will be temporary closed
    • Traffic will be diverted to Eastbound lane and East-West direction will be controlled by temporary traffic signals
Picture
*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
  • Phase 1:
    • Station to Edmund – COMPLETED
  • Phase 2:
    • Beechgrove to McClellan – ONGOING
    • McClellan to Station – upcoming
    • Edmund to Main/Queen Intersection – upcoming
    • McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
 
In the Event of an Emergency or Gas Shut Off, please contact the following Enbridge staff:
  • First call – Field inspector – Phil Sanderson – 416-998-0568
  • Second call – Escalation call, Management – Jeff Bruce – 416-819-3517
  • Emergency Dispatch – 1-833-872-3477
 
FOR YOUR INFORMATION:
  • Dufferin County will be completing road resurfacing and select culvert replacements on County Road 23, between Dufferin County Road 23 (B-Line) and Peel Regional Road 136 (Porterfield Road)
  • During construction of Phase 2, Canada Post relocated existing super boxes (mail boxes) from N/W corners of McClellan/Main and King/Main to Station Street, between Alton School and Library.  New mailboxes will be reinstalled to original location once construction is complete
Picture
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

3/19/2019

0 Comments

 
+ Staff finalized paperwork and executed the documents; project is awarded to Fermar Paving Limited
+ The Contractor is anticipated to mobilize on site Wednesday, March 20, 2019 and set up signage, barrels and a field office
+ Pre-Construction meeting will take place on Monday, March 25, 2019

The Contractor is anticipated to commence work on the new storm sewer and water-mains Tuesday, March 26, 2019:
- New storm sewer installation on Queen Street East, between railway tracks and Main Street and on Main Street South, between Queen Street East and McClellan Road
- Relocation of the water-main on Main Street South, between Station Street and Edmund Street


*** Please note Enbridge Gas Distribution (NPL Canada) continues to complete gas relocations in the Village in phases:
Phase 1:
+ Station Street to Edmund Street – The new main and all service transfers will be completed by Friday, March 22, 2019; the old main along the West side of the Cemetery slope will be decommissioned and abandoned
Phase 2:
+ Station Street to McClellan Road – Work will commence on Monday, March 25, 2019
+ Main/Queen Intersection to Edmund Street – Work will commence in two weeks
+ McClellan Road Substation (relocation of the station from N/W to S/W corner) – upcoming
+ Beechgrove to McClellan – upcoming
March 26, 2019
0 Comments

Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

3/1/2019

0 Comments

 
What are we doing?
+ Improving Main Street South and Queen Street East, including road reconstruction, drainage and boulevard improvements, providing on-street parking, decorative street lighting, streetscaping enhancements and landscaping.

The work includes, but is not limited to:
+ asphalt removal, road excavation and boulevard grading;
+ installation of new:
  • storm sewer
  • retaining wall structure at the cemetery with architectural finishes
  • vegetated retaining wall
  • barrier curbs
  • decorative coloured pattern concrete splash pads
  • wider concrete sidewalks
  • decorative architectural streetlighting
  • rest areas with street furniture
  • gateway features at South end (traffic calming measures); and
  • parkette area with town clock
+ pavement with wider lanes
+ improved pavement markings
l+ andscaping
+ minor related works; and,
+ Improvements to Caledon Fire Station 301 parking lot.


Where?
+ Main Street South, from Beechgrove Sideroad to Queen Street East
+ Queen Street East from Main Street South to East of Railway Tracks

​When?

+ Start: March, 2019
+ Finish: December 20, 2019, weather permitting
Picture
main_street_2019-03-01.pdf
File Size: 81 kb
File Type: pdf
Download File

0 Comments

​Update on Phase 2 Alton Village Streetscaping from Serguei Kabanov, Project Manager

2/26/2019

0 Comments

 
In the last month, the Region of Peel
+ Completed tendering processes and awarded Phase 2 works to Fermar Paving Limited http://www.fermarltd.com/
+ Staff are currently finalizing paperwork and executing the documents
+ The Contractor is anticipated to commence work mid to late March
​

*** Please note: Enbridge Gas Distribution retained NPL Canada https://nplcanada.ca/ to complete gas relocations in the Village. The contractor will be mobilizing the site this week, February 28/19, weather permitting. Work will commence in phases:
​

Phase 1:
+ Station Street to Edmund Street
Phase 2:
+ Main/Queen Intersection to Edmund Street
+ Station Street to McClellan Road

Work will include:
+ Relocation of gas mains and services along Main Street South, between Queen Street East and Beechgrove Sideroad
+ Relocation of gas substation from N/W to S/W corner of McClellan Road
0 Comments

​Alton Village Streets Update:

2/25/2019

0 Comments

 
Queen Street East and Main Street South – Just a reminder that The Region of Peel Phase 2 of the Alton Streetscaping project is expected to start in March 2019 the community has been advised that work will commence between Beechgrove and McClellan mid-July.
AVA continues to post up-dates provided by the Region of Peel on both here our Facebook Page; https://www.facebook.com/AltonVillageAssociation

Village Square Updates:
AVA has been working the Town to secure water for the Square. We have received great news the installation of water to the Square will be happening in the Spring. This water hookup will allow us to get our water feature operating, and also help us to maintain the Village Gardens. We want to thank Brian Baird, Manager of Parks at the Town of Caledon, for his hard work and ongoing support for our Village Square. The Town of Caledon is also going to take over looking after the Garbage at the Village Square. We want to remind dog lovers, that when walking your pets in the Square to please ensure that you clean-up after them. Your help to keep our Square a pleasant place to stroll is appreciated. The AVA encourages all residents and visitors to enjoy the use of our picnic tables and benches in the Village Square, and did you know that you can pick berries from the bushes along the east boarder of the Square in the spring?

Alton Pump Track, an outdoor bike track located next to the Alton Ball Diamond is well underway. The base is installed, and if the weather cooperates it is hoped that the track is completed in June.

Neighbourhood Watch Information Session:

https://www.facebook.com/events/362631001131307/
Caledon Village Place, March 18th. 2019, 6:00 p.m. to 9:00 p.m.

Thank You Mike Weston - Mike spends many hours clearing, flooding and grooming the ice rink at Alton Ball Park . Mike your hard work is certainly appreciated by the community.
0 Comments
<<Previous
Forward>>

    Categories

    All
    AVA Event
    Community Event
    Construction
    Playground
    Streetscaping

    Archives

    August 2023
    April 2023
    February 2023
    November 2022
    September 2022
    April 2022
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017

    RSS Feed

Powered by Create your own unique website with customizable templates.